Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2412 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $872 | $135 | n/a |
LS2412 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,854 | $5,915 | n/a |
LS2411 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,595 | $50 | n/a |
LS2411 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $266 | $45 | n/a |
LS2411 # 03 Y:2024 | 03 | 2024 | IMPROVE SPACE COMFORT CONDITIONING | $26,395 | $18,900 | n/a |
LS2411 # 04 Y:2024 | 04 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,962 | $12,050 | n/a |
LS2411 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $72,136 | $480,000 | n/a |
SF0619 # 01 Y:2024 | 01 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $4,612 | $0 | n/a |
SF0619 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,589 | $220 | n/a |
SF0619 # 03 Y:2024 | 03 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $241 | $0 | n/a |
SF0619 # 04 Y:2024 | 04 | 2024 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $39,174 | $7,044 | n/a |
SF0619 # 05 Y:2024 | 05 | 2024 | USE MINIMUM STEAM OPERATING PRESSURE | $7,106 | $2,700 | n/a |
SF0619 # 06 Y:2024 | 06 | 2024 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $90,155 | $37,058 | n/a |
SF0619 # 07 Y:2024 | 07 | 2024 | INSTALL STEAM TRAP | $531,211 | $270,719 | n/a |
SF0619 # 08 Y:2024 | 08 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,389 | $4,926 | n/a |
SF0619 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $2,201 | $2,875 | n/a |
SF0619 # 10 Y:2024 | 10 | 2024 | INSTALL OCCUPANCY SENSORS | $292 | $785 | n/a |
SF0619 # 11 Y:2024 | 11 | 2024 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $52,391 | $160,125 | n/a |
SF0619 # 12 Y:2024 | 12 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,993 | $16,268 | n/a |
CI0032 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,412 | $313,000 | n/a |
CI0032 # 02 Y:2024 | 02 | 2024 | INSULATE BARE EQUIPMENT | $10,726 | $2,419 | n/a |
CI0032 # 03 Y:2024 | 03 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,326 | $24,000 | n/a |
CI0032 # 04 Y:2024 | 04 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $8,168 | $13,563 | n/a |
CI0032 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,401 | $0 | n/a |
CI0032 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,536 | $22,885 | n/a |