Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21,186
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0252 # 03 Y:2025 | 03 | 2025 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $28,847 | $27,000 | n/a |
DL0252 # 04 Y:2025 | 04 | 2025 | UPGRADE CONTROLS ON COMPRESSORS | $8,172 | $9,000 | n/a |
DL0252 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $15,540 | $1,500 | n/a |
DL0252 # 06 Y:2025 | 06 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,945 | $9,000 | n/a |
DL0252 # 07 Y:2025 | 07 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $657 | $1,000 | n/a |
CI0044 # 01 Y:2024 | 01 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $43,028 | $180,000 | n/a |
CI0044 # 02 Y:2024 | 02 | 2024 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $15,529 | $100,000 | n/a |
CI0044 # 03 Y:2024 | 03 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,426 | $93,790 | n/a |
CI0044 # 04 Y:2024 | 04 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $10,940 | $13,970 | n/a |
CI0044 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,848 | $9,000 | n/a |
CI0044 # 06 Y:2024 | 06 | 2024 | INSULATE BARE EQUIPMENT | $5,585 | $8,530 | n/a |
CI0044 # 07 Y:2024 | 07 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,415 | $5,000 | n/a |
CI0044 # 08 Y:2024 | 08 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,241 | $1,500 | n/a |
LE0592 # 01 Y:2025 | 01 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,457 | $100 | n/a |
LE0592 # 02 Y:2025 | 02 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $40,366 | $3,000 | n/a |
LE0592 # 03 Y:2025 | 03 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,485 | $7,000 | n/a |
LE0592 # 04 Y:2025 | 04 | 2025 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $2,361 | $3,915 | n/a |
LE0592 # 05 Y:2025 | 05 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,195 | $4,000 | n/a |
LE0592 # 06 Y:2025 | 06 | 2025 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $12,213 | $24,000 | n/a |
LE0592 # 07 Y:2025 | 07 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,842 | $126,000 | n/a |
LE0592 # 08 Y:2025 | 08 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,177 | $26,000 | n/a |
LE0592 # 09 Y:2025 | 09 | 2025 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $513 | $2,500 | n/a |
IC0321 # 01 Y:2025 | 01 | 2025 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $693 | $644 | n/a |
IC0321 # 02 Y:2025 | 02 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $93,480 | $390,298 | n/a |
IC0321 # 03 Y:2025 | 03 | 2025 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $730 | $1,774 | n/a |