IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

233

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0046 # 05 Y:2003 05 2003 INSTALL OCCUPANCY SENSORS $6,168 $750 Not Implemented
UU0046 # 06 Y:2003 06 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,686 $7,815 Implemented
UU0046 # 07 Y:2003 07 2003 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $5,727 $3,889 Not Implemented
UU0044 # 01 Y:2003 01 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,210 $3,508 Not Implemented
UU0044 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,130 $0 Implemented
UU0044 # 03 Y:2003 03 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,390 $5,000 Not Implemented
UU0044 # 04 Y:2003 04 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,476 $800 Implemented
UU0044 # 05 Y:2003 05 2003 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,070 $0 Not Implemented
UU0044 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,211 $7,976 Not Implemented
UU0040 # 01 Y:2003 01 2003 OPTIMIZE PLANT POWER FACTOR $1 $0 Not Implemented
UU0040 # 02 Y:2003 02 2003 UTILIZE A LESS EXPENSIVE COOLING METHOD $150 $0 Not Implemented
UU0040 # 03 Y:2003 03 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,957 $0 Not Implemented
UU0040 # 04 Y:2003 04 2003 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $2,285 $0 Not Implemented
UU0040 # 05 Y:2003 05 2003 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $1 $0 Not Implemented
UU0040 # 06 Y:2003 06 2003 RECOVER WASTE HEAT FROM EQUIPMENT $57 $55 Not Implemented
UU0034 # 01 Y:2002 01 2002 OPTIMIZE PLANT POWER FACTOR $3,790 $2,000 Not Implemented
UU0034 # 02 Y:2002 02 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $2,627 $3,621 Not Implemented
UU0034 # 03 Y:2002 03 2002 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,938 $1,000 Not Implemented
UU0034 # 04 Y:2002 04 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $10,560 $0 Not Implemented
UU0034 # 05 Y:2002 05 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,759 $800 Not Implemented
UU0032 # 01 Y:2002 01 2002 MOVE BOILER TO MORE EFFICIENT LOCATION $83 $86 Not Implemented
UU0032 # 02 Y:2002 02 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $4,155 $12,000 Not Implemented
UU0032 # 03 Y:2002 03 2002 OPTIMIZE PLANT POWER FACTOR $988 $2,604 Not Implemented
UU0032 # 04 Y:2002 04 2002 INSTALL OCCUPANCY SENSORS $4,743 $600 Not Implemented
UU0032 # 05 Y:2002 05 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,517 $17,563 Not Implemented