Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1016 # 01 Y:2019 | 01 | 2019 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $27,210 | $730 | Not Implemented |
OK1016 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,028 | $28,358 | Implemented |
OK1016 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,766 | $9,480 | Not Implemented |
OK1016 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,330 | $0 | Implemented |
OK1016 # 05 Y:2019 | 05 | 2019 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,523 | $0 | Not Implemented |
OK1016 # 06 Y:2019 | 06 | 2019 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $885 | $4,860 | Not Implemented |
OK1016 # 07 Y:2019 | 07 | 2019 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $485 | $636 | Implemented |
MI0360 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO HEAT WATER | $36,147 | $40,234 | Implemented |
MI0360 # 02 Y:2019 | 02 | 2019 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $34,382 | $15,720 | Not Implemented |
MI0360 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,735 | $3,600 | Implemented |
MI0360 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $5,613 | $13,630 | Implemented |
MI0360 # 05 Y:2019 | 05 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,707 | $3,634 | Implemented |
MI0360 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,330 | $3,023 | Implemented |
MI0360 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,445 | $1,980 | Implemented |
MI0360 # 08 Y:2019 | 08 | 2019 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $1,675 | $3,764 | Implemented |
MI0360 # 09 Y:2019 | 09 | 2019 | INSTALL OCCUPANCY SENSORS | $751 | $211 | Implemented |
MI0360 # 10 Y:2019 | 10 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $684 | $100 | Not Implemented |
MI0360 # 11 Y:2019 | 11 | 2019 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $476 | $868 | Implemented |
SF0546 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,375 | $542 | Implemented |
SF0546 # 02 Y:2019 | 02 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,228 | $705 | Not Implemented |
SF0546 # 03 Y:2019 | 03 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $13,458 | $28,920 | Not Implemented |
SF0546 # 04 Y:2019 | 04 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $17,331 | $84,932 | Not Implemented |
UF0534 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $53,586 | $333,760 | Not Implemented |
UF0534 # 02 Y:2019 | 02 | 2019 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $8,685 | $27,820 | Not Implemented |
UF0534 # 03 Y:2019 | 03 | 2019 | INSTALL DESICCANT HUMIDITY CONTROL SYSTEM | $8,399 | $570 | Not Implemented |