Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
38
matching recommendationsSIC | 2013 | Sausages And Other Prepared Meats |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0284 # 08 Y:2007 | 08 | 2007 | INSULATE BARE EQUIPMENT | $155 | $102 | Not Implemented |
LL0284 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,030 | $451 | Not Implemented |
LL0284 # 06 Y:2007 | 06 | 2007 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,700 | $2,074 | Not Implemented |
LL0284 # 01 Y:2007 | 01 | 2007 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $52,170 | $49,000 | Not Implemented |
LL0284 # 02 Y:2007 | 02 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $33,682 | $1,600 | Not Implemented |
LL0284 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,045 | $12,575 | Not Implemented |
LL0284 # 04 Y:2007 | 04 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $16,900 | $1,500 | Not Implemented |
LL0284 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,314 | $2,100 | Not Implemented |
UD0763 # 06 Y:2007 | 06 | 2007 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $1,835 | $3,670 | Not Implemented |
UD0763 # 05 Y:2007 | 05 | 2007 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $2,275 | $0 | Not Implemented |
UD0763 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,551 | $8,100 | Not Implemented |
UD0763 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,945 | $57,910 | Not Implemented |
UD0763 # 02 Y:2007 | 02 | 2007 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $30,994 | $8,900 | Implemented |
UD0763 # 01 Y:2007 | 01 | 2007 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $36,135 | $5,242 | Implemented |
IC0127 # 02 Y:2007 | 02 | 2007 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $800 | $440 | Implemented |
IC0127 # 09 Y:2007 | 09 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,282 | $0 | Implemented |
IC0127 # 08 Y:2007 | 08 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $2,137 | $1,000 | Implemented |
IC0127 # 07 Y:2007 | 07 | 2007 | INSULATE BARE EQUIPMENT | $3,818 | $886 | Implemented |
IC0127 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,336 | $20,976 | Implemented |
IC0127 # 05 Y:2007 | 05 | 2007 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $36,459 | $0 | Implemented |
IC0127 # 04 Y:2007 | 04 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $120 | $1,026 | Implemented |
IC0127 # 03 Y:2007 | 03 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,063 | $51,889 | Implemented |
IC0127 # 01 Y:2007 | 01 | 2007 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $14,659 | $0 | Implemented |
IC0127 # 10 Y:2007 | 10 | 2007 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $22,675 | $50,711 | Implemented |
WV0353 # 14 Y:2007 | 14 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $796 | $3,000 | Implemented |