Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,313
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0516 # 07 Y:2018 | 07 | 2018 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $32,827 | $20,000 | Implemented |
SF0516 # 08 Y:2018 | 08 | 2018 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $28,367 | $15,956 | Implemented |
SF0516 # 09 Y:2018 | 09 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $43,509 | $36,186 | Implemented |
SF0516 # 11 Y:2018 | 11 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,207 | $7,506 | Implemented |
AM0732 # 01 Y:2017 | 01 | 2017 | TREAT AND REUSE RINSE WATERS | $19,732 | $5,800 | Implemented |
AM0732 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,470 | $6,750 | Implemented |
OK0958 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,735 | $9,149 | Implemented |
OK0958 # 03 Y:2016 | 03 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $7,914 | $3,250 | Implemented |
OK0958 # 04 Y:2016 | 04 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,461 | $2,000 | Implemented |
OK0958 # 09 Y:2016 | 09 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,455 | $0 | Implemented |
OK0958 # 10 Y:2016 | 10 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $24,151 | $70,000 | Implemented |
OK0958 # 11 Y:2016 | 11 | 2016 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $16,955 | $100,000 | Implemented |
OK0958 # 12 Y:2016 | 12 | 2016 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,996 | $0 | Implemented |
NC0583 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,519 | $6,412 | Implemented |
NC0583 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,025 | $200 | Implemented |
NC0583 # 06 Y:2017 | 06 | 2017 | DEVELOP A REPAIR/REPLACE POLICY | $2,529 | $5,865 | Implemented |
NC0583 # 07 Y:2017 | 07 | 2017 | INSULATE FEEDWATER TANK | $665 | $1,106 | Implemented |
IA0566 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,976 | $49,834 | Implemented |
IA0566 # 02 Y:2016 | 02 | 2016 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,279 | $6,724 | Implemented |
IA0566 # 03 Y:2016 | 03 | 2016 | INSTALL OCCUPANCY SENSORS | $3,889 | $5,100 | Implemented |
IA0566 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,660 | $6,945 | Implemented |
IA0566 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,966 | $195 | Implemented |
IA0566 # 06 Y:2016 | 06 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,284 | $1,000 | Implemented |
IA0566 # 07 Y:2016 | 07 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $592 | $70 | Implemented |
WM0095 # 03 Y:2016 | 03 | 2016 | REPAIR AND ELIMINATE STEAM LEAKS | $7,438 | $1,560 | Implemented |