Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

39

matching recommendations
Reset
SIC 2022 Cheese, Natural And Processed
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0710 # 07 Y:2018 07 2018 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $12,550 $1,000 Not Implemented
OR0710 # 06 Y:2018 06 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,410 $3,742 Not Implemented
OR0710 # 05 Y:2018 05 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,922 $12,567 Not Implemented
OR0710 # 01 Y:2018 01 2018 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $80,821 $56,937 Not Implemented
OR0710 # 04 Y:2018 04 2018 REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE $19,538 $19,269 Not Implemented
OR0710 # 03 Y:2018 03 2018 UPGRADE CONTROLS ON COMPRESSORS $15,485 $1,280 Not Implemented
OR0710 # 02 Y:2018 02 2018 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $31,220 $60,550 Not Implemented
OR0656 # 05 Y:2015 05 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $7,282 $22,500 Implemented
OR0656 # 02 Y:2015 02 2015 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $188,688 $247,000 Implemented
OR0656 # 04 Y:2015 04 2015 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $317,386 $0 Not Implemented
OR0656 # 01 Y:2015 01 2015 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $2,308,919 $1,300,000 Implemented
OR0656 # 03 Y:2015 03 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,591 $27,789 Implemented
OR0559 # 06 Y:2010 06 2010 USE HEAT EXCHANGE FLUIDS INSTEAD OF STEAM IN PIPELINE TRACING SYSTEMS $26,673 $64,505 Not Implemented
OR0559 # 05 Y:2010 05 2010 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $12,771 $40,000 Not Implemented
OR0559 # 04 Y:2010 04 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,495 $3,495 Not Implemented
OR0559 # 03 Y:2010 03 2010 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,126 $1 Not Implemented
OR0559 # 02 Y:2010 02 2010 USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER $7,300 $6,712 Not Implemented
OR0559 # 01 Y:2010 01 2010 INSTALL OCCUPANCY SENSORS $25,044 $36,275 Not Implemented
OR0559 # 07 Y:2010 07 2010 INSTALL REPLACEMENT DOORS $7,531 $16,375 Not Implemented
OR0501 # 06 Y:2006 06 2006 INSTALL OCCUPANCY SENSORS $8,560 $100 Implemented
OR0501 # 07 Y:2006 07 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,100 $0 Implemented
OR0501 # 05 Y:2006 05 2006 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $25,000 $3,400 Not Implemented
OR0501 # 04 Y:2006 04 2006 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $31,700 $105 Implemented
OR0501 # 03 Y:2006 03 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $41,300 $59,700 Implemented
OR0501 # 02 Y:2006 02 2006 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $72,600 $1 Implemented