Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
512
matching recommendationsSIC | 2024 | Ice Cream And Frozen Desserts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0180 # 06 Y:1985 | 06 | 1985 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,822 | $0 | Not Implemented |
OK0181 # 01 Y:1985 | 01 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,786 | $4,300 | Not Implemented |
OK0181 # 02 Y:1985 | 02 | 1985 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,120 | $6,500 | Not Implemented |
OK0181 # 03 Y:1985 | 03 | 1985 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $3,832 | $2,940 | Not Implemented |
OK0181 # 04 Y:1985 | 04 | 1985 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,131 | $579 | Not Implemented |
OK0181 # 05 Y:1985 | 05 | 1985 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $649 | $592 | Implemented |
OK0181 # 06 Y:1985 | 06 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,428 | $57 | Implemented |
KU0165 # 01 Y:1985 | 01 | 1985 | INCREASE AMOUNT OF CONDENSATE RETURNED | $28,837 | $33,000 | Implemented |
KU0165 # 02 Y:1985 | 02 | 1985 | HEAT WATER WITH EXHAUST HEAT | $20,949 | $37,000 | Implemented |
KU0165 # 03 Y:1985 | 03 | 1985 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,822 | $9,000 | Not Implemented |
KU0165 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,248 | $4,815 | Implemented |
KU0165 # 05 Y:1985 | 05 | 1985 | IMPROVE LUBRICATION PRACTICES | $10,224 | $8,000 | Implemented |
KU0165 # 06 Y:1985 | 06 | 1985 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,321 | $1,020 | Implemented |
KU0165 # 07 Y:1985 | 07 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,984 | $50 | Implemented |
KU0165 # 08 Y:1985 | 08 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $998 | $450 | Implemented |
KU0165 # 09 Y:1985 | 09 | 1985 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $468 | $400 | Implemented |
KU0165 # 10 Y:1985 | 10 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $484 | $400 | Implemented |
MA0010 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $712 | $135 | Implemented |
MA0010 # 02 Y:1984 | 02 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $574 | $200 | Implemented |
MA0010 # 03 Y:1984 | 03 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $4,782 | $1,260 | Implemented |
MA0010 # 04 Y:1984 | 04 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $8,400 | $6,300 | Implemented |
MA0010 # 05 Y:1984 | 05 | 1984 | OPERATE BOILERS ON HIGH FIRE SETTING | $3,110 | $4,000 | Implemented |
MA0010 # 06 Y:1984 | 06 | 1984 | HEAT WATER WITH EXHAUST HEAT | $16,603 | $22,000 | Not Implemented |
MA0010 # 07 Y:1984 | 07 | 1984 | RESCHEDULE AND REARRANGE MULTIPLE-SOURCE HEATING SYSTEMS | $2,680 | $8,130 | Implemented |
MA0003 # 01 Y:1984 | 01 | 1984 | REPAIR OR REPLACE STEAM TRAPS | $14,697 | $0 | Implemented |