Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
44
matching recommendationsSIC | 2035 | Pickles, Sauces, And Salad Dressings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0549 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $1,214 | Implemented |
SF0549 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,719 | $0 | Implemented |
SF0549 # 06 Y:2020 | 06 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $403 | $1,776 | Implemented |
SF0549 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,204 | $25,635 | Implemented |
SF0549 # 08 Y:2020 | 08 | 2020 | USE FOG NOZZLES / SPRAY RINSING INSTEAD OF IMMERSION RINSING | $22,925 | $1,810 | Implemented |
SF0408 # 06 Y:2012 | 06 | 2012 | USE SOLAR HEAT TO MAKE ELECTRICTY | $231,136 | $1,514,353 | Implemented |
SF0408 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $3,255 | $11,297 | Implemented |
SF0408 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,111 | $0 | Implemented |
SF0408 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,571 | $80 | Implemented |
SD0436 # 02 Y:2011 | 02 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,180 | $2,000 | Implemented |
SD0436 # 07 Y:2011 | 07 | 2011 | INCREASE AMOUNT OF CONDENSATE RETURNED | $12,828 | $20,000 | Implemented |
SD0436 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,598 | $52,274 | Implemented |
SD0436 # 04 Y:2011 | 04 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,787 | $1,535 | Implemented |
SD0436 # 03 Y:2011 | 03 | 2011 | INSTALL OCCUPANCY SENSORS | $7,888 | $6,050 | Implemented |
SD0436 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,198 | $2,100 | Implemented |
SD0502 # 01 Y:2010 | 01 | 2010 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $17,800 | $10,000 | Implemented |
SD0502 # 02 Y:2010 | 02 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,170 | $1,000 | Implemented |
SD0502 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,905 | $161,162 | Implemented |
SD0419 # 05 Y:2009 | 05 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,905 | $161,162 | Implemented |
SD0419 # 04 Y:2009 | 04 | 2009 | INCREASE AMOUNT OF CONDENSATE RETURNED | $15,940 | $2,263 | Implemented |
SD0419 # 02 Y:2009 | 02 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,170 | $1,000 | Implemented |
SD0419 # 01 Y:2009 | 01 | 2009 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $17,800 | $10,000 | Implemented |
SF0274 # 03 Y:2004 | 03 | 2004 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $146 | $30 | Implemented |
SF0274 # 08 Y:2004 | 08 | 2004 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,380 | $260 | Implemented |
SF0274 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $346 | $318 | Implemented |