Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
62
matching recommendationsSIC | 204 | Grain Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0234 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,415 | $1,250 | Implemented |
LL0234 # 02 Y:2005 | 02 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $69,333 | $500 | Implemented |
LL0234 # 08 Y:2005 | 08 | 2005 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $24,050 | $7,000 | Implemented |
LL0234 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $393 | $300 | Implemented |
LL0234 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $136 | $200 | Implemented |
LL0234 # 05 Y:2005 | 05 | 2005 | USE PHOTOCELL CONTROLS | $501 | $100 | Implemented |
LL0233 # 01 Y:2005 | 01 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $56,386 | $73,240 | Implemented |
LL0233 # 09 Y:2005 | 09 | 2005 | USE PHOTOCELL CONTROLS | $2,451 | $450 | Implemented |
LL0233 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,837 | $3,400 | Implemented |
LL0233 # 04 Y:2005 | 04 | 2005 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $17,072 | $2,900 | Implemented |
LL0233 # 05 Y:2005 | 05 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $15,391 | $2,800 | Implemented |
LL0233 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,619 | $14,000 | Implemented |
LL0232 # 04 Y:2005 | 04 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $43,777 | $6,100 | Implemented |
LL0232 # 03 Y:2005 | 03 | 2005 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $44,802 | $20,000 | Implemented |
LL0232 # 09 Y:2005 | 09 | 2005 | USE PHOTOCELL CONTROLS | $2,101 | $700 | Implemented |
LL0232 # 12 Y:2005 | 12 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,185 | $1,120 | Implemented |
LL0232 # 08 Y:2005 | 08 | 2005 | AIR CONDITION ONLY SPACE NECESSARY | $5,876 | $60 | Implemented |
LL0232 # 13 Y:2005 | 13 | 2005 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $7,350 | $3,010 | Implemented |
LL0232 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,717 | $2,000 | Implemented |
LL0232 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $35,683 | $27,760 | Implemented |
AR0134 # 02 Y:1998 | 02 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,071 | $180 | Implemented |
AR0134 # 03 Y:1998 | 03 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,183 | $0 | Implemented |
AR0134 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,050 | $360 | Implemented |
AR0134 # 06 Y:1998 | 06 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $119 | $0 | Implemented |
AR0134 # 08 Y:1998 | 08 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $52,140 | $3,000 | Implemented |