Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

122

matching recommendations
Reset
SIC 204 Grain Mill Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0759 # 04 Y:2008 04 2008 KEEP BOILER TUBES CLEAN $158,338 $6,876 Not Implemented
OK0759 # 03 Y:2008 03 2008 OPERATE BOILERS ON HIGH FIRE SETTING $18,069 $17,500 Not Implemented
OK0759 # 06 Y:2008 06 2008 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $15,331 $1,619 Not Implemented
OK0759 # 01 Y:2008 01 2008 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $10,284 $11,736 Implemented
OK0759 # 05 Y:2008 05 2008 INSTALL / REPAIR INSULATION ON STEAM LINES $14,208 $5,500 Not Implemented
OK0759 # 02 Y:2008 02 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,620 $967 Implemented
KU0517 # 06 Y:1999 06 1999 INSTALL AUTOMATIC PACKING EQUIPMENT $42,140 $99,000 Not Implemented
KU0517 # 05 Y:1999 05 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $240 $250 Implemented
KU0517 # 04 Y:1999 04 1999 INSTALL OCCUPANCY SENSORS $1,100 $1,950 Implemented
KU0517 # 03 Y:1999 03 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,430 $350 Implemented
KU0517 # 02 Y:1999 02 1999 OPTIMIZE PLANT POWER FACTOR $2,750 $2,400 Not Implemented
KU0517 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,360 $2,580 Implemented
KU0516 # 07 Y:1999 07 1999 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL $1,322,390 $2,171,500 Not Implemented
KU0516 # 08 Y:1999 08 1999 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $49,760 $35,000 Implemented
KU0516 # 05 Y:1999 05 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,220 $870 Implemented
KU0516 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,520 $8,930 Implemented
KU0516 # 04 Y:1999 04 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,770 $670 Implemented
KU0516 # 01 Y:1999 01 1999 OPTIMIZE PLANT POWER FACTOR $17,580 $24,400 Implemented
KU0516 # 06 Y:1999 06 1999 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $7,990 $5,000 Not Implemented
KU0516 # 03 Y:1999 03 1999 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $8,490 $18,930 Not Implemented
KU0499 # 06 Y:1998 06 1998 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $250 $430 n/a
KU0499 # 07 Y:1998 07 1998 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $10,490 $8,000 n/a
KU0499 # 03 Y:1998 03 1998 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,100 $930 n/a
KU0499 # 08 Y:1998 08 1998 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $59,360 $440 n/a
KU0499 # 02 Y:1998 02 1998 INSULATE BARE EQUIPMENT $2,180 $1,820 n/a