Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,095
matching recommendationsSIC | 204 | Grain Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0587 # 08 Y:1999 | 08 | 1999 | INSULATE BARE EQUIPMENT | $250 | $525 | n/a |
CO0451 # 01 Y:1999 | 01 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,190 | $6,250 | Not Implemented |
CO0451 # 02 Y:1999 | 02 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,080 | $4,000 | Implemented |
CO0451 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $220 | $20 | Implemented |
CO0451 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $190 | $320 | Implemented |
CO0451 # 05 Y:1999 | 05 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $20 | $0 | Not Implemented |
ME0273 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,815 | $5,192 | n/a |
ME0273 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,750 | $4,260 | n/a |
ME0273 # 03 Y:1999 | 03 | 1999 | USE SOLAR HEAT FOR HEAT | $1,220 | $5,472 | n/a |
ME0273 # 04 Y:1999 | 04 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $421 | $0 | n/a |
ME0273 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $309 | $100 | n/a |
ME0273 # 06 Y:1999 | 06 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $23,318 | $212,393 | n/a |
ME0273 # 07 Y:1999 | 07 | 1999 | REDUCE SCRAP PRODUCTION | $13,050 | $22,253 | n/a |
ME0273 # 08 Y:1999 | 08 | 1999 | ELIMINATE/REDUCE AN OPERATION | $1,716 | $612 | n/a |
ND0324 # 01 Y:1999 | 01 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $802 | $1,525 | Not Implemented |
ND0324 # 02 Y:1999 | 02 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,051 | $250 | Implemented |
ND0324 # 03 Y:1999 | 03 | 1999 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $7,258 | $30,000 | Implemented |
ND0324 # 04 Y:1999 | 04 | 1999 | DEVELOP A REPAIR/REPLACE POLICY | $52,604 | $41,503 | Not Implemented |
ND0324 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $459 | $1,800 | Not Implemented |
ND0324 # 06 Y:1999 | 06 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $-252 | $0 | Not Implemented |
ND0324 # 07 Y:1999 | 07 | 1999 | REDUCE SCRAP PRODUCTION | $11,250 | $7,200 | Implemented |
KU0517 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,360 | $2,580 | Implemented |
KU0517 # 02 Y:1999 | 02 | 1999 | OPTIMIZE PLANT POWER FACTOR | $2,750 | $2,400 | Not Implemented |
KU0517 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,430 | $350 | Implemented |
KU0517 # 04 Y:1999 | 04 | 1999 | INSTALL OCCUPANCY SENSORS | $1,100 | $1,950 | Implemented |