Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
67
matching recommendationsSIC | 204 | Grain Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0587 # 08 Y:1999 | 08 | 1999 | INSULATE BARE EQUIPMENT | $250 | $525 | n/a |
OK0587 # 07 Y:1999 | 07 | 1999 | INSULATE BARE EQUIPMENT | $252 | $1,028 | n/a |
OK0587 # 01 Y:1999 | 01 | 1999 | INSTALL SYSTEM TO COLLECT SCRAP | $20,078 | $2,250 | n/a |
OK0587 # 02 Y:1999 | 02 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $16,905 | $0 | n/a |
OK0587 # 03 Y:1999 | 03 | 1999 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $7,398 | $31,705 | n/a |
OK0587 # 04 Y:1999 | 04 | 1999 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $3,795 | $0 | n/a |
OK0587 # 05 Y:1999 | 05 | 1999 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,193 | $3,150 | n/a |
OK0587 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $891 | $24 | n/a |
CO0451 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $190 | $320 | Implemented |
CO0451 # 05 Y:1999 | 05 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $20 | $0 | Not Implemented |
CO0451 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $220 | $20 | Implemented |
CO0451 # 01 Y:1999 | 01 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,190 | $6,250 | Not Implemented |
CO0451 # 02 Y:1999 | 02 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,080 | $4,000 | Implemented |
ME0273 # 06 Y:1999 | 06 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $23,318 | $212,393 | n/a |
ME0273 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $309 | $100 | n/a |
ME0273 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,815 | $5,192 | n/a |
ME0273 # 07 Y:1999 | 07 | 1999 | REDUCE SCRAP PRODUCTION | $13,050 | $22,253 | n/a |
ME0273 # 08 Y:1999 | 08 | 1999 | ELIMINATE/REDUCE AN OPERATION | $1,716 | $612 | n/a |
ME0273 # 03 Y:1999 | 03 | 1999 | USE SOLAR HEAT FOR HEAT | $1,220 | $5,472 | n/a |
ME0273 # 04 Y:1999 | 04 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $421 | $0 | n/a |
ME0273 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,750 | $4,260 | n/a |
ND0324 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $459 | $1,800 | Not Implemented |
ND0324 # 04 Y:1999 | 04 | 1999 | DEVELOP A REPAIR/REPLACE POLICY | $52,604 | $41,503 | Not Implemented |
ND0324 # 03 Y:1999 | 03 | 1999 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $7,258 | $30,000 | Implemented |
ND0324 # 02 Y:1999 | 02 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,051 | $250 | Implemented |