Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
145
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0591 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $460,292 | $1,330,000 | Not Implemented |
UF0591 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $48,128 | $44,635 | Implemented |
UF0591 # 07 Y:2023 | 07 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,713 | $0 | Implemented |
UF0591 # 08 Y:2023 | 08 | 2023 | INSTALL TURBULATORS | $1,724 | $7,500 | Not Implemented |
UF0591 # 05 Y:2023 | 05 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $12,470 | $19,320 | Implemented |
UF0591 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,896 | $8,591 | Implemented |
UF0591 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $45,481 | $66,747 | Implemented |
UF0591 # 06 Y:2023 | 06 | 2023 | INSTALL SUB-METERING EQUIPMENT | $2,168 | $8,880 | Implemented |
UF0590 # 06 Y:2023 | 06 | 2023 | INSTALL SUB-METERING EQUIPMENT | $10,106 | $11,100 | Implemented |
UF0590 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,955 | $25,440 | Implemented |
UF0590 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $90,544 | $67,849 | Implemented |
UF0590 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $101,164 | $60,322 | Not Implemented |
UF0590 # 07 Y:2023 | 07 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $3,034 | $528 | Implemented |
UF0590 # 03 Y:2023 | 03 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $16,705 | $11,574 | Implemented |
UF0590 # 04 Y:2023 | 04 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $31,115 | $12,420 | Implemented |
UF0590 # 08 Y:2023 | 08 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $79,607 | $10,000 | Implemented |
UF0574 # 03 Y:2022 | 03 | 2022 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $22,318 | $12,420 | Implemented |
UF0574 # 15 Y:2022 | 15 | 2022 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,082 | $88 | Implemented |
UF0574 # 01 Y:2022 | 01 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $57,729 | $322,608 | Implemented |
UF0574 # 14 Y:2022 | 14 | 2022 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $18,108 | $45,538 | Implemented |
UF0574 # 08 Y:2022 | 08 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,103 | $14,366 | Not Implemented |
UF0574 # 09 Y:2022 | 09 | 2022 | INSTALL TURBULATORS | $2,101 | $7,500 | Not Implemented |
UF0574 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,896 | $25,258 | Implemented |
UF0574 # 04 Y:2022 | 04 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,484 | $20,340 | Implemented |
UF0574 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $38,315 | $45,847 | Implemented |