Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
882
matching recommendationsSIC | 2051 | Bread, Cake, And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0562 # 01 Y:2024 | 01 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $4,513 | $320 | Implemented |
LE0562 # 07 Y:2024 | 07 | 2024 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $3,491 | $8,000 | Implemented |
LE0562 # 05 Y:2024 | 05 | 2024 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $727 | $1,000 | Implemented |
LE0562 # 02 Y:2024 | 02 | 2024 | INSTALL OCCUPANCY SENSORS | $1,612 | $350 | Implemented |
SF0612 # 02 Y:2024 | 02 | 2024 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $175 | $59 | Implemented |
SF0612 # 01 Y:2024 | 01 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,332 | $226 | Implemented |
GT0965 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $34,014 | $1,850 | Implemented |
GT0965 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,164 | $800 | Implemented |
GT0965 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $281 | $927 | Implemented |
UF0591 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,896 | $8,591 | Implemented |
UF0591 # 07 Y:2023 | 07 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,713 | $0 | Implemented |
GT0964 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $78,169 | $1,850 | Implemented |
GT0964 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $18,786 | $50,570 | Implemented |
UF0591 # 06 Y:2023 | 06 | 2023 | INSTALL SUB-METERING EQUIPMENT | $2,168 | $8,880 | Implemented |
UF0591 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $45,481 | $66,747 | Implemented |
UF0591 # 05 Y:2023 | 05 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $12,470 | $19,320 | Implemented |
UF0591 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $48,128 | $44,635 | Implemented |
UF0590 # 06 Y:2023 | 06 | 2023 | INSTALL SUB-METERING EQUIPMENT | $10,106 | $11,100 | Implemented |
UF0590 # 04 Y:2023 | 04 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $31,115 | $12,420 | Implemented |
UF0590 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $90,544 | $67,849 | Implemented |
UF0590 # 07 Y:2023 | 07 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $3,034 | $528 | Implemented |
UF0590 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,955 | $25,440 | Implemented |
UF0590 # 03 Y:2023 | 03 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $16,705 | $11,574 | Implemented |
UF0590 # 08 Y:2023 | 08 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $79,607 | $10,000 | Implemented |
OR0768 # 01 Y:2023 | 01 | 2023 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $18,535 | $8,125 | Implemented |