Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,843
matching recommendationsSIC | 2051 | Bread, Cake, And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CC0012 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,343 | $16,000 | n/a |
CC0012 # 05 Y:2022 | 05 | 2022 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $3,233 | $0 | n/a |
CC0012 # 06 Y:2022 | 06 | 2022 | REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE | $7,230 | $30,000 | n/a |
CC0012 # 07 Y:2022 | 07 | 2022 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $47,241 | $125,000 | n/a |
UA0267 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $677 | $901 | Implemented |
UA0267 # 04 Y:2022 | 04 | 2022 | OPTIMIZE PLANT POWER FACTOR | $2,388 | $1,682 | Not Implemented |
UA0267 # 03 Y:2022 | 03 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $2,954 | $1,360 | Implemented |
UA0267 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,033 | $1,000 | Implemented |
UA0267 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $13,660 | $51,749 | Not Implemented |
UA0266 # 06 Y:2022 | 06 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $894 | $558 | Not Implemented |
UA0266 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,871 | $22,132 | Not Implemented |
UA0266 # 04 Y:2022 | 04 | 2022 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,089 | $188 | Not Implemented |
UA0266 # 03 Y:2022 | 03 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $1,950 | $865 | Not Implemented |
UA0266 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,514 | $8,397 | Not Implemented |
UA0266 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $19,219 | $1,000 | Not Implemented |
TT0291 # 01 Y:2023 | 01 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $44,264 | $3,287 | Not Implemented |
TT0291 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,378 | $10,100 | Implemented |
TT0291 # 03 Y:2023 | 03 | 2023 | PURCHASE APPROPRIATELY SIZED MATERIAL | $18,022 | $87,000 | Not Implemented |
TT0291 # 04 Y:2023 | 04 | 2023 | USE OPTIMUM THICKNESS INSULATION | $14,929 | $45,390 | Not Implemented |
TT0291 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,663 | $1,500 | Implemented |
TT0291 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $2,088 | $4,500 | Not Implemented |
SF0595 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,469 | $5,620 | Implemented |
SF0595 # 06 Y:2023 | 06 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,280 | $7,191 | Implemented |
SF0595 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,989 | $21,654 | Implemented |
SF0595 # 04 Y:2023 | 04 | 2023 | HEAT WATER WITH EXHAUST HEAT | $37,173 | $32,818 | Not Implemented |