Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
258
matching recommendationsSIC | 2086 | Bottled And Canned Soft Drinks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0574 # 08 Y:2010 | 08 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $545 | $0 | Not Implemented |
AM0574 # 09 Y:2010 | 09 | 2010 | INSULATE BARE EQUIPMENT | $240 | $185 | Not Implemented |
AM0574 # 10 Y:2010 | 10 | 2010 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $111 | $0 | Not Implemented |
AM0527 # 01 Y:2007 | 01 | 2007 | OPTIMIZE PLANT POWER FACTOR | $33,106 | $56,785 | Implemented |
AM0527 # 02 Y:2007 | 02 | 2007 | PAY BILLS ON TIME TO AVOID LATE FEES | $28,915 | $0 | Implemented |
AM0527 # 03 Y:2007 | 03 | 2007 | INSTALL OCCUPANCY SENSORS | $19,815 | $27,489 | Implemented |
AM0527 # 04 Y:2007 | 04 | 2007 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $6,604 | $0 | Not Implemented |
AM0527 # 05 Y:2007 | 05 | 2007 | USE PHOTOCELL CONTROLS | $200 | $22 | Implemented |
AM0527 # 06 Y:2007 | 06 | 2007 | INSULATE BARE EQUIPMENT | $457 | $28 | Implemented |
TA0130 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,192 | $0 | Implemented |
TA0130 # 02 Y:2006 | 02 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $81 | $252 | Implemented |
TA0130 # 03 Y:2006 | 03 | 2006 | OPTIMIZE PLANT POWER FACTOR | $10,795 | $22,000 | Implemented |
AM0508 # 01 Y:2006 | 01 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $8,400 | $2,190 | Not Implemented |
AM0508 # 02 Y:2006 | 02 | 2006 | MODIFY STARTUP/SHUTDOWN TIMES | $7,024 | $0 | Not Implemented |
AM0508 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,950 | $500 | Not Implemented |
AM0508 # 04 Y:2006 | 04 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,700 | $270 | Not Implemented |
AM0508 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $295 | $140 | Not Implemented |
AM0508 # 06 Y:2006 | 06 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $210 | $50 | Not Implemented |
AM0508 # 07 Y:2006 | 07 | 2006 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $190 | $0 | Not Implemented |
AM0508 # 08 Y:2006 | 08 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,980 | $500 | Not Implemented |
AM0482 # 01 Y:2005 | 01 | 2005 | TREAT AND REUSE RINSE WATERS | $50,000 | $2,000 | Implemented |
AM0482 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,940 | $500 | Implemented |
AM0482 # 03 Y:2005 | 03 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,210 | $0 | Implemented |
AM0482 # 04 Y:2005 | 04 | 2005 | USE SYNTHETIC LUBRICANT | $1,020 | $0 | Implemented |
AM0482 # 05 Y:2005 | 05 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $640 | $0 | Implemented |