Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,340
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0596 # 07 Y:2012 | 07 | 2012 | TREAT AND REUSE RINSE WATERS | $48,291 | $10,000 | Implemented |
NC0448 # 03 Y:2012 | 03 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,746 | $5,600 | Implemented |
NC0448 # 04 Y:2012 | 04 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,740 | $400 | Implemented |
NC0448 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $880 | $200 | Implemented |
BD0406 # 04 Y:2012 | 04 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,394 | $3,000 | Implemented |
BD0406 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,404 | $500 | Implemented |
BD0406 # 10 Y:2012 | 10 | 2012 | INSTALL OCCUPANCY SENSORS | $1,808 | $1,350 | Implemented |
BD0406 # 11 Y:2012 | 11 | 2012 | INSTALL TURBULATORS | $772 | $1,500 | Implemented |
BD0406 # 13 Y:2012 | 13 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $254 | $10 | Implemented |
GT0884 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,890 | $44,900 | Implemented |
GT0884 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $4,290 | $210 | Implemented |
GT0884 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,400 | $600 | Implemented |
GT0884 # 07 Y:2011 | 07 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $29,550 | $2,000 | Implemented |
SF0398 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,251 | $0 | Implemented |
SF0398 # 02 Y:2011 | 02 | 2011 | REPAIR AND ELIMINATE STEAM LEAKS | $4,412 | $0 | Implemented |
SF0398 # 03 Y:2011 | 03 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $23,241 | $0 | Implemented |
SF0398 # 04 Y:2011 | 04 | 2011 | AIR CONDITION ONLY SPACE NECESSARY | $4,965 | $424 | Implemented |
SF0398 # 05 Y:2011 | 05 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $112,927 | $56,209 | Implemented |
SF0398 # 07 Y:2011 | 07 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $975 | $2,405 | Implemented |
DL0066 # 01 Y:2011 | 01 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,960 | $1,035 | Implemented |
DL0066 # 03 Y:2011 | 03 | 2011 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,460 | $2,000 | Implemented |
DL0066 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,015 | $4,000 | Implemented |
MA0669 # 01 Y:2011 | 01 | 2011 | REPLACE BOILER | $28,774 | $63,300 | Implemented |
MA0669 # 03 Y:2011 | 03 | 2011 | OPTIMIZE PLANT POWER FACTOR | $10,179 | $11,190 | Implemented |
MA0669 # 04 Y:2011 | 04 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,848 | $1,500 | Implemented |