Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
74
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0602 # 08 Y:2020 | 08 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $263 | $1,060 | Implemented |
WV0602 # 09 Y:2020 | 09 | 2020 | DEVELOP A REPAIR/REPLACE POLICY | $154 | $568 | Implemented |
WV0602 # 04 Y:2020 | 04 | 2020 | INSULATE BARE EQUIPMENT | $1,512 | $2,197 | Implemented |
WV0602 # 05 Y:2020 | 05 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $743 | $1,348 | Not Implemented |
WV0602 # 06 Y:2020 | 06 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $322 | $299 | Not Implemented |
DL0168 # 02 Y:2016 | 02 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,380 | $200 | Not Implemented |
DL0168 # 01 Y:2016 | 01 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,910 | $200 | Not Implemented |
DL0168 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,120 | $1,000 | Not Implemented |
DL0168 # 04 Y:2016 | 04 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $67,220 | $62,600 | Not Implemented |
DL0168 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $4,520 | $6,800 | Not Implemented |
DL0168 # 06 Y:2016 | 06 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,385 | $7,400 | Not Implemented |
DL0168 # 07 Y:2016 | 07 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,320 | $4,980 | Not Implemented |
DL0168 # 08 Y:2016 | 08 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,000 | $67,370 | Not Implemented |
DL0168 # 09 Y:2016 | 09 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $27,900 | $190,600 | Not Implemented |
LE0348 # 08 Y:2012 | 08 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $120 | $40 | Not Implemented |
LE0348 # 07 Y:2012 | 07 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,956 | $5,700 | Implemented |
LE0348 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,650 | $1,600 | Implemented |
LE0348 # 05 Y:2012 | 05 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $2,368 | $2,300 | Implemented |
LE0348 # 04 Y:2012 | 04 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,951 | $1,940 | Not Implemented |
LE0348 # 03 Y:2012 | 03 | 2012 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $12,235 | $43,550 | Not Implemented |
LE0348 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,828 | $5,000 | Not Implemented |
LE0348 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,702 | $24,000 | Implemented |
LE0262 # 10 Y:2007 | 10 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,332 | $2,000 | Not Implemented |
LE0262 # 07 Y:2007 | 07 | 2007 | REPAIR OR REPLACE STEAM TRAPS | $16,954 | $4,200 | Not Implemented |
LE0262 # 08 Y:2007 | 08 | 2007 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,938 | $500 | Not Implemented |