Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
660
matching recommendationsSIC | 2099 | Food Preparations, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW0016 # 01 Y:2008 | 01 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $29,638 | $0 | Implemented |
UW0016 # 05 Y:2008 | 05 | 2008 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $4,625 | $8,550 | Implemented |
UW0016 # 04 Y:2008 | 04 | 2008 | INSULATE BARE EQUIPMENT | $7,000 | $500 | Implemented |
SF0355 # 01 Y:2008 | 01 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $904 | $1,040 | Implemented |
SF0355 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,950 | $26,488 | Implemented |
SF0355 # 04 Y:2008 | 04 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $282 | $1,174 | Implemented |
CO0609 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,170 | $300 | Implemented |
CO0609 # 03 Y:2007 | 03 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $161 | $846 | Implemented |
MI0160 # 01 Y:2008 | 01 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,466 | $1,032 | Implemented |
MI0160 # 03 Y:2008 | 03 | 2008 | UTILIZE SENSORS CONTROLLING ROOF AND WALL OPENINGS | $16,476 | $474 | Implemented |
MI0160 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,705 | $17,226 | Implemented |
MI0160 # 06 Y:2008 | 06 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,319 | $24 | Implemented |
CO0593 # 02 Y:2006 | 02 | 2006 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $6,180 | $60 | Implemented |
CO0593 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,750 | $120 | Implemented |
CO0593 # 07 Y:2006 | 07 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,550 | $6,000 | Implemented |
AM0511 # 01 Y:2006 | 01 | 2006 | OPTIMIZE PLANT POWER FACTOR | $18,600 | $59,000 | Implemented |
AM0511 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,160 | $150 | Implemented |
WI0506 # 05 Y:2006 | 05 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,795 | $800 | Implemented |
WI0506 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,430 | $0 | Implemented |
WI0506 # 07 Y:2006 | 07 | 2006 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $990 | $1,500 | Implemented |
WI0506 # 04 Y:2006 | 04 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,464 | $1,000 | Implemented |
WI0506 # 02 Y:2006 | 02 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $1,049 | $0 | Implemented |
WI0506 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,973 | $16,740 | Implemented |
GT0811 # 01 Y:2005 | 01 | 2005 | IMPROVE LUBRICATION PRACTICES | $3,405 | $0 | Implemented |
GT0811 # 02 Y:2005 | 02 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $28,824 | $20,700 | Implemented |