IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

33

matching recommendations
Reset
SIC 22 Textile Mill Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UL2210 # 07 Y:2022 07 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,109 $20,000 Not Implemented
UL2210 # 01 Y:2022 01 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,273 $11,544 Implemented
UL2210 # 08 Y:2022 08 2022 USE SOLAR HEAT TO HEAT WATER $59,693 $150,000 Not Implemented
UL2210 # 02 Y:2022 02 2022 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $6,394 $0 Implemented
UL2210 # 03 Y:2022 03 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,208 $0 Implemented
UL2210 # 04 Y:2022 04 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,235 $1,600 Implemented
UL2210 # 05 Y:2022 05 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $86,119 $765,706 Not Implemented
UL2210 # 06 Y:2022 06 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,669 $20,000 Not Implemented
UL0117 # 02 Y:1995 02 1995 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $4,441 $22,850 Not Implemented
UL0117 # 10 Y:1995 10 1995 REMOVE SLUDGE FROM TANKS ON A REGULAR BASIS $3,600 $5,000 Not Implemented
UL0117 # 09 Y:1995 09 1995 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $1,660 $1,000 Not Implemented
UL0117 # 08 Y:1995 08 1995 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,100 $5,000 Not Implemented
UL0117 # 07 Y:1995 07 1995 TREAT AND REUSE RINSE WATERS $70,000 $8,000 Not Implemented
UL0117 # 06 Y:1995 06 1995 METER WASTE WATER $8,000 $1,000 Not Implemented
UL0117 # 05 Y:1995 05 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,993 $2,077 Not Implemented
UL0117 # 04 Y:1995 04 1995 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $1,593 $1,146 Not Implemented
UL0117 # 03 Y:1995 03 1995 OPTIMIZE PLANT POWER FACTOR $1,046 $808 Not Implemented
UL0117 # 01 Y:1995 01 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $149 $25 Not Implemented
TN0499 # 01 Y:1993 01 1993 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $40,654 $49 Implemented
TN0499 # 09 Y:1993 09 1993 INSULATE BARE EQUIPMENT $443 $170 Implemented
TN0499 # 08 Y:1993 08 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,297 $380 Not Implemented
TN0499 # 07 Y:1993 07 1993 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,740 $0 Not Implemented
TN0499 # 06 Y:1993 06 1993 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,725 $350 Not Implemented
TN0499 # 05 Y:1993 05 1993 INSULATE BARE EQUIPMENT $9,913 $30 Not Implemented
TN0499 # 04 Y:1993 04 1993 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $14,164 $0 Not Implemented