Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
15
matching recommendationsSIC | 2261 | Finishing Plants, Cotton |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0754 # 01 Y:2003 | 01 | 2003 | BURN A LESS EXPENSIVE GRADE OF FUEL | $24,451 | $69,000 | Implemented |
GT0754 # 02 Y:2003 | 02 | 2003 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $146,600 | $104,000 | Implemented |
GT0754 # 03 Y:2003 | 03 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $10,080 | $0 | Implemented |
GT0754 # 05 Y:2003 | 05 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $840 | $678 | Implemented |
GT0754 # 06 Y:2003 | 06 | 2003 | INCREASE AMOUNT OF CONDENSATE RETURNED | $87,548 | $12,750 | Implemented |
GT0754 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,324 | $2,271 | Implemented |
GT0754 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,607 | $1,414 | Implemented |
GT0754 # 11 Y:2003 | 11 | 2003 | RECOVER AND REUSE COOLING WATER | $293,681 | $201,600 | Implemented |
GT0594 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,591 | $9,855 | Implemented |
GT0594 # 03 Y:1996 | 03 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $13,380 | $0 | Implemented |
GT0594 # 05 Y:1996 | 05 | 1996 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $112,836 | $405,000 | Implemented |
GT0338 # 01 Y:1988 | 01 | 1988 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $30,000 | $6,670 | Implemented |
GT0338 # 02 Y:1988 | 02 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $15,600 | $500 | Implemented |
GT0338 # 05 Y:1988 | 05 | 1988 | INSULATE BARE EQUIPMENT | $800 | $1,320 | Implemented |
GT0338 # 06 Y:1988 | 06 | 1988 | REPAIR AND ELIMINATE STEAM LEAKS | $5,280 | $4,075 | Implemented |