Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
29
matching recommendationsSIC | 228 | Yarn And Thread Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0161 # 04 Y:1997 | 04 | 1997 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $4,370 | $5,000 | Not Implemented |
HO0161 # 03 Y:1997 | 03 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $723 | $385 | Implemented |
HO0161 # 07 Y:1997 | 07 | 1997 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $12,500 | $2,000 | Implemented |
HO0161 # 02 Y:1997 | 02 | 1997 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,635 | $1,878 | Not Implemented |
HO0161 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,362 | $11,311 | Implemented |
HO0161 # 06 Y:1997 | 06 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,130 | $100 | Not Implemented |
HO0161 # 05 Y:1997 | 05 | 1997 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $480 | $100 | Implemented |
NC0112 # 06 Y:1997 | 06 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $7,750 | $10,280 | n/a |
NC0112 # 07 Y:1997 | 07 | 1997 | EXPAND OPERATIONS INTO UNUSED SPACE | $60,000 | $1,080 | n/a |
NC0112 # 05 Y:1997 | 05 | 1997 | RECOVER AND REUSE WASTE MATERIAL | $16,220 | $260 | n/a |
NC0112 # 04 Y:1997 | 04 | 1997 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,698 | $300 | n/a |
NC0112 # 03 Y:1997 | 03 | 1997 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $1,601 | $20 | n/a |
NC0112 # 02 Y:1997 | 02 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,183 | $397 | n/a |
NC0112 # 01 Y:1997 | 01 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $9,780 | $0 | n/a |
OK0523 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,325 | $132,000 | Not Implemented |
OK0523 # 02 Y:1997 | 02 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $65,338 | $74,935 | Implemented |
OK0523 # 03 Y:1997 | 03 | 1997 | INSTALL OCCUPANCY SENSORS | $1,405 | $1,188 | Not Implemented |
OK0523 # 04 Y:1997 | 04 | 1997 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $72,212 | $16,000 | Implemented |
OK0523 # 05 Y:1997 | 05 | 1997 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $2,478 | $6,900 | Implemented |
OK0523 # 06 Y:1997 | 06 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,326 | $1,658 | Not Implemented |
OK0523 # 07 Y:1997 | 07 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,077 | $0 | Implemented |
GT0607 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,960 | $62,150 | Implemented |
GT0607 # 06 Y:1997 | 06 | 1997 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,086 | $15,000 | Implemented |
GT0607 # 05 Y:1997 | 05 | 1997 | IMPROVE PROCESS CONTROL TO PREVENT SPILLS OF MATERIAL | $90,000 | $21,000 | Implemented |
GT0607 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,568 | $29,830 | Implemented |