Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
46
matching recommendationsSIC | 232 | Men's And Boys' Furnishings, Work Clothing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0434 # 07 Y:1991 | 07 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,785 | $0 | Implemented |
TN0434 # 06 Y:1991 | 06 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35 | $128 | Implemented |
TN0434 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $173 | $410 | Implemented |
TN0434 # 04 Y:1991 | 04 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $117 | $115 | Implemented |
TN0434 # 03 Y:1991 | 03 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,504 | $3,650 | Implemented |
TN0434 # 02 Y:1991 | 02 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,163 | $240 | Implemented |
TN0434 # 01 Y:1991 | 01 | 1991 | USE MINIMUM STEAM OPERATING PRESSURE | $1,745 | $2,550 | Implemented |
TN0446 # 01 Y:1991 | 01 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $5,675 | $2,700 | Implemented |
TN0446 # 04 Y:1991 | 04 | 1991 | INSTALL / REPAIR INSULATION ON STEAM LINES | $488 | $165 | Implemented |
TN0446 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $1,068 | $0 | Implemented |
TN0446 # 06 Y:1991 | 06 | 1991 | INSULATE BARE EQUIPMENT | $338 | $859 | Implemented |
TN0446 # 02 Y:1991 | 02 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,089 | $1,590 | Implemented |
TN0446 # 03 Y:1991 | 03 | 1991 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $507 | $0 | Implemented |
OK0354 # 01 Y:1991 | 01 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $7,243 | $10,424 | Implemented |
OK0354 # 08 Y:1991 | 08 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $188 | $0 | Implemented |
OK0354 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $85 | $0 | Implemented |
OK0354 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $533 | $202 | Implemented |
OK0354 # 05 Y:1991 | 05 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $6,989 | $4,290 | Implemented |
OK0354 # 04 Y:1991 | 04 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $172 | $0 | Implemented |
OK0354 # 03 Y:1991 | 03 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $50 | $0 | Implemented |
OK0354 # 02 Y:1991 | 02 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $430 | $0 | Implemented |
OK0346 # 02 Y:1991 | 02 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,919 | $0 | Implemented |
OK0346 # 03 Y:1991 | 03 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,122 | $866 | Implemented |
OK0346 # 04 Y:1991 | 04 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $1,923 | $1,500 | Implemented |
OK0346 # 01 Y:1991 | 01 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $857 | $0 | Implemented |