Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
772
matching recommendationsSIC | 232 | Men's And Boys' Furnishings, Work Clothing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0446 # 01 Y:1991 | 01 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $5,675 | $2,700 | Implemented |
TN0446 # 02 Y:1991 | 02 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,089 | $1,590 | Implemented |
TN0446 # 03 Y:1991 | 03 | 1991 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $507 | $0 | Implemented |
TN0446 # 04 Y:1991 | 04 | 1991 | INSTALL / REPAIR INSULATION ON STEAM LINES | $488 | $165 | Implemented |
TN0446 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $1,068 | $0 | Implemented |
TN0446 # 06 Y:1991 | 06 | 1991 | INSULATE BARE EQUIPMENT | $338 | $859 | Implemented |
OK0354 # 01 Y:1991 | 01 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $7,243 | $10,424 | Implemented |
OK0354 # 02 Y:1991 | 02 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $430 | $0 | Implemented |
OK0354 # 03 Y:1991 | 03 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $50 | $0 | Implemented |
OK0354 # 04 Y:1991 | 04 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $172 | $0 | Implemented |
OK0354 # 05 Y:1991 | 05 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $6,989 | $4,290 | Implemented |
OK0354 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $533 | $202 | Implemented |
OK0354 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $85 | $0 | Implemented |
OK0354 # 08 Y:1991 | 08 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $188 | $0 | Implemented |
OK0346 # 01 Y:1991 | 01 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $857 | $0 | Implemented |
OK0346 # 02 Y:1991 | 02 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,919 | $0 | Implemented |
OK0346 # 03 Y:1991 | 03 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,122 | $866 | Implemented |
OK0346 # 04 Y:1991 | 04 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $1,923 | $1,500 | Implemented |
OK0346 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $613 | $0 | Implemented |
MA0210 # 01 Y:1991 | 01 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $300 | $136 | Implemented |
MA0210 # 02 Y:1991 | 02 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $191 | $350 | Implemented |
MA0210 # 03 Y:1991 | 03 | 1991 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $651 | $2,764 | Implemented |
MA0210 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $136 | $47 | Implemented |
MA0210 # 05 Y:1991 | 05 | 1991 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $151 | $405 | Implemented |
MA0210 # 06 Y:1991 | 06 | 1991 | CONVERT COMBUSTION EQUIPMENT TO BURN OIL | $1,286 | $2,375 | Implemented |