Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,223
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NT0036 # 03 Y:2025 | 03 | 2025 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,825 | $0 | n/a |
NT0036 # 04 Y:2025 | 04 | 2025 | OPTIMIZE PLANT POWER FACTOR | $6,170 | $16,268 | n/a |
NT0036 # 01 Y:2025 | 01 | 2025 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $688 | $0 | n/a |
NT0036 # 02 Y:2025 | 02 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,972 | $5,609 | n/a |
DL0245 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,536 | $53,470 | n/a |
DL0245 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,607 | $6,000 | n/a |
DL0245 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,089 | $9,630 | n/a |
DL0245 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $774 | $0 | n/a |
DL0245 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,824 | $1,592 | n/a |
DL0245 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,149 | $0 | n/a |
GT0984 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,806 | $6,230 | n/a |
GT0984 # 07 Y:2024 | 07 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $775 | $1,950 | n/a |
GT0984 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,669 | $3,750 | n/a |
GT0984 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,281 | $1,850 | n/a |
GT0984 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $2,912 | $7,675 | n/a |
GT0984 # 04 Y:2024 | 04 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,676 | $1,650 | n/a |
GT0984 # 09 Y:2024 | 09 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $48,984 | $1,053,552 | n/a |
GT0984 # 05 Y:2024 | 05 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $219 | $225 | n/a |
GT0984 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $875 | $400 | n/a |
LS2420 # 06 Y:2024 | 06 | 2024 | INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE | $11,877 | $51,800 | n/a |
LS2420 # 03 Y:2024 | 03 | 2024 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $16,356 | $15,100 | n/a |
LS2420 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $1,025 | $25 | n/a |
LS2420 # 01 Y:2024 | 01 | 2024 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $7,485 | $0 | n/a |
LS2420 # 04 Y:2024 | 04 | 2024 | UPGRADE CONTROLS ON COMPRESSORS | $9,307 | $21,000 | n/a |
LS2420 # 05 Y:2024 | 05 | 2024 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $24,642 | $68,828 | n/a |