Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,223
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0156 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,712 | $2,024 | Implemented |
UU0156 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,961 | $2,600 | Not Implemented |
UU0156 # 03 Y:2019 | 03 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,768 | $12,634 | Not Implemented |
UU0156 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,497 | $2,300 | Implemented |
UU0156 # 05 Y:2019 | 05 | 2019 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $1,315 | $2,600 | Not Implemented |
UU0156 # 06 Y:2019 | 06 | 2019 | INSULATE BARE EQUIPMENT | $3,874 | $3,125 | Implemented |
UF0538 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,744 | $52,547 | Implemented |
UF0538 # 02 Y:2019 | 02 | 2019 | INSTALL SKYLIGHTS | $11,989 | $45,500 | Implemented |
UF0538 # 03 Y:2019 | 03 | 2019 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $11,027 | $7,692 | Implemented |
UF0538 # 04 Y:2019 | 04 | 2019 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,964 | $6,180 | Implemented |
OR0722 # 01 Y:2019 | 01 | 2019 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $42,047 | $1,000 | Implemented |
OR0722 # 02 Y:2019 | 02 | 2019 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $17,875 | $0 | Implemented |
OR0722 # 03 Y:2019 | 03 | 2019 | USE OPTIMUM TEMPERATURE | $6,191 | $0 | Not Implemented |
OR0722 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,107 | $0 | Implemented |
OR0722 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,488 | $1,110 | Not Implemented |
OR0722 # 06 Y:2019 | 06 | 2019 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $28,751 | $129,960 | Not Implemented |
OR0722 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,941 | $15,179 | Not Implemented |
NC0636 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,929 | $16,627 | Implemented |
NC0636 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $362 | $871 | Not Implemented |
NC0636 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $184 | $60 | Implemented |
NC0636 # 04 Y:2019 | 04 | 2019 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $27,892 | $85,000 | Not Implemented |
IP0120 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,145 | $4 | Implemented |
IP0120 # 02 Y:2019 | 02 | 2019 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $835 | $0 | Implemented |
IP0120 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $348 | $0 | Not Implemented |
IP0120 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $223 | $22 | Implemented |