IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,167

matching recommendations
Reset
SIC 24 Lumber And Wood Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0379 # 05 Y:2000 05 2000 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $2,229 $0 Not Implemented
OR0379 # 06 Y:2000 06 2000 COMBINE UTILITY METERS $1,715 $4,000 Not Implemented
OR0379 # 07 Y:2000 07 2000 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $9,628 $48,484 Implemented
OR0379 # 08 Y:2000 08 2000 OPTIMIZE PLANT POWER FACTOR $7,013 $19,600 Not Implemented
OR0379 # 09 Y:2000 09 2000 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $1,026,000 $1,337,500 Not Implemented
OR0378 # 01 Y:2000 01 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,287 $1,000 Implemented
OR0378 # 02 Y:2000 02 2000 UPGRADE CONTROLS ON COMPRESSORS $2,967 $4,000 Implemented
OR0378 # 03 Y:2000 03 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $732 $0 Implemented
OR0378 # 04 Y:2000 04 2000 OPTIMIZE PLANT POWER FACTOR $2,340 $6,500 Not Implemented
OR0378 # 05 Y:2000 05 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,503 $4,033 Implemented
OR0378 # 06 Y:2000 06 2000 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $1,506 $3,800 Implemented
OR0378 # 07 Y:2000 07 2000 MINIMIZE WATER USAGE $1,233 $4,701 Not Implemented
OR0370 # 01 Y:2000 01 2000 USE OPTIMUM TEMPERATURE $27,300 $0 Implemented
OR0370 # 02 Y:2000 02 2000 USE OPTIMUM TEMPERATURE $4,900 $650 Implemented
OR0370 # 03 Y:2000 03 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,673 $2,050 Implemented
OR0370 # 04 Y:2000 04 2000 RECOVER WASTE HEAT FROM EQUIPMENT $2,748 $1,909 Implemented
OR0370 # 05 Y:2000 05 2000 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $92,680 $0 Implemented
OR0370 # 06 Y:2000 06 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,089 $12,821 Not Implemented
OR0366 # 01 Y:2000 01 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,963 $0 Implemented
OR0366 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $365 $0 Implemented
OR0366 # 03 Y:2000 03 2000 OPTIMIZE PLANT POWER FACTOR $359 $1,200 Not Implemented
OR0366 # 04 Y:2000 04 2000 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,570 $7,800 Not Implemented
OR0366 # 05 Y:2000 05 2000 INSTALL TIMERS AND/OR THERMOSTATS $28,188 $1,410 Implemented
OR0365 # 01 Y:2000 01 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,216 $4,300 Implemented
OR0365 # 02 Y:2000 02 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $618 $0 Not Implemented