Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,167
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0798 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,382 | $4,736 | n/a |
OR0798 # 05 Y:2024 | 05 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $13,899 | $90,000 | n/a |
OR0798 # 02 Y:2024 | 02 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $733 | $2,196 | n/a |
OR0798 # 06 Y:2024 | 06 | 2024 | USE RADIANT HEATER FOR SPOT HEATING | $921 | $8,538 | n/a |
OR0798 # 01 Y:2024 | 01 | 2024 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $1,715 | $502 | n/a |
OR0798 # 07 Y:2024 | 07 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $6,445 | $64,276 | n/a |
OR0798 # 04 Y:2024 | 04 | 2024 | UPGRADE OBSOLETE EQUIPMENT | $19,584 | $93,860 | n/a |
OR0794 # 03 Y:2024 | 03 | 2024 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $20,545 | $92,473 | n/a |
OR0794 # 06 Y:2024 | 06 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $13,489 | $12,623 | n/a |
OR0794 # 02 Y:2024 | 02 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,287 | $5,523 | n/a |
OR0794 # 01 Y:2024 | 01 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,236 | $1,629 | n/a |
OR0794 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,153 | $7,546 | n/a |
OR0794 # 04 Y:2024 | 04 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $12,662 | $67,250 | n/a |
OR0785 # 01 Y:2023 | 01 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,209,151 | $28,500 | Not Implemented |
OR0785 # 04 Y:2023 | 04 | 2023 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,475 | $16,140 | Not Implemented |
OR0785 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,141 | $4,510 | Not Implemented |
OR0785 # 02 Y:2023 | 02 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $4,224 | $1,583 | Not Implemented |
OR0785 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $323 | $0 | Implemented |
OR0778 # 02 Y:2023 | 02 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,178 | $0 | Not Implemented |
OR0778 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,010 | $8,010 | Not Implemented |
OR0778 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,119 | $0 | Not Implemented |
OR0767 # 02 Y:2023 | 02 | 2023 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $172,773 | $37,200 | Implemented |
OR0767 # 03 Y:2023 | 03 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $300,390 | $200,000 | Implemented |
OR0767 # 01 Y:2023 | 01 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,793 | $0 | Not Implemented |
OR0767 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,167 | $14,238 | Not Implemented |