Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
115
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0071 # 03 Y:1989 | 03 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $106 | $181 | Implemented |
OR0071 # 02 Y:1989 | 02 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,682 | $5,000 | Implemented |
OR0071 # 05 Y:1989 | 05 | 1989 | REDUCE FLUID FLOW RATES | $4,615 | $12,560 | Implemented |
OR0071 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,915 | $500 | Not Implemented |
OR0071 # 04 Y:1989 | 04 | 1989 | OPTIMIZE PLANT POWER FACTOR | $900 | $2,250 | Not Implemented |
GT0388 # 06 Y:1989 | 06 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25 | $15 | Implemented |
OR0068 # 07 Y:1989 | 07 | 1989 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $4,272 | $2,814 | Not Implemented |
OR0068 # 08 Y:1989 | 08 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $704 | $576 | Not Implemented |
OR0068 # 02 Y:1989 | 02 | 1989 | INSTALL SET-BACK TIMERS | $5,010 | $0 | Implemented |
OR0069 # 04 Y:1989 | 04 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $59 | $45 | Implemented |
OR0068 # 11 Y:1989 | 11 | 1989 | REDUCE OR ELIMINATE WASTE | $268,559 | $1,000,000 | Not Implemented |
OR0068 # 10 Y:1989 | 10 | 1989 | OPTIMIZE PLANT POWER FACTOR | $2,056 | $3,300 | Not Implemented |
OR0068 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,642 | $0 | Not Implemented |
OR0068 # 03 Y:1989 | 03 | 1989 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,409 | $0 | Implemented |
GT0388 # 07 Y:1989 | 07 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $70 | $45 | Not Implemented |
OR0068 # 04 Y:1989 | 04 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $17,258 | $370 | Not Implemented |
GT0388 # 05 Y:1989 | 05 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $190 | $410 | Implemented |
GT0388 # 04 Y:1989 | 04 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $626 | $0 | Implemented |
GT0388 # 03 Y:1989 | 03 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $278 | $230 | Implemented |
GT0388 # 02 Y:1989 | 02 | 1989 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,300 | $10,000 | Not Implemented |
GT0388 # 01 Y:1989 | 01 | 1989 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,330 | $3,000 | Not Implemented |
OR0068 # 06 Y:1989 | 06 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,848 | $500 | Implemented |
OR0069 # 03 Y:1989 | 03 | 1989 | INSTALL SET-BACK TIMERS | $725 | $100 | Implemented |
OR0069 # 06 Y:1989 | 06 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $952 | $300 | Implemented |
OR0068 # 09 Y:1989 | 09 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,552 | $3,000 | Implemented |