Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
128
matching recommendationsSIC | 242 | Sawmills And Planing Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0298 # 07 Y:2000 | 07 | 2000 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $20,769 | $0 | Not Implemented |
ME0298 # 06 Y:2000 | 06 | 2000 | REDUCE SCRAP PRODUCTION | $61,470 | $204,600 | Not Implemented |
ME0296 # 13 Y:2000 | 13 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $1,875 | $965 | Not Implemented |
ME0296 # 11 Y:2000 | 11 | 2000 | IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) | $8,450 | $52,500 | Not Implemented |
ME0296 # 01 Y:2000 | 01 | 2000 | BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT | $625,184 | $1,387,500 | Not Implemented |
ME0296 # 03 Y:2000 | 03 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,070 | $4,700 | Not Implemented |
ME0296 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,377 | $2,124 | Not Implemented |
ME0296 # 06 Y:2000 | 06 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $752 | $490 | Not Implemented |
ME0296 # 08 Y:2000 | 08 | 2000 | USE PHOTOCELL CONTROLS | $387 | $600 | Not Implemented |
ME0296 # 07 Y:2000 | 07 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $666 | $1,088 | Not Implemented |
ME0296 # 05 Y:2000 | 05 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $856 | $890 | Not Implemented |
ME0296 # 10 Y:2000 | 10 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $212 | $518 | Not Implemented |
ME0296 # 04 Y:2000 | 04 | 2000 | PAY UTILITY BILLS ON TIME | $1,617 | $0 | Not Implemented |
ME0296 # 09 Y:2000 | 09 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $375 | $230 | Not Implemented |
ME0296 # 12 Y:2000 | 12 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $437,500 | $784,300 | Not Implemented |
ME0292 # 09 Y:2000 | 09 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $264 | $380 | Not Implemented |
ME0292 # 01 Y:2000 | 01 | 2000 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $13,365 | $13,000 | Not Implemented |
ME0292 # 03 Y:2000 | 03 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $6,527 | $9,000 | Not Implemented |
ME0292 # 02 Y:2000 | 02 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,056 | $26,450 | Not Implemented |
ME0292 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,822 | $340 | Implemented |
ME0292 # 06 Y:2000 | 06 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,025 | $1,373 | Not Implemented |
ME0292 # 11 Y:2000 | 11 | 2000 | USE OPTIMUM THICKNESS INSULATION | $34 | $72 | Not Implemented |
ME0292 # 13 Y:2000 | 13 | 2000 | SELL COMBUSTIBLE WASTE | $4,000 | $12,000 | Not Implemented |
ME0292 # 12 Y:2000 | 12 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $8,700 | $9,500 | Not Implemented |
ME0292 # 15 Y:2000 | 15 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $2,500 | $1,550 | Not Implemented |