Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
113
matching recommendationsSIC | 242 | Sawmills And Planing Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0405 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,599 | $4,500 | Implemented |
OR0405 # 04 Y:2001 | 04 | 2001 | OPTIMIZE PLANT POWER FACTOR | $17,987 | $28,200 | Implemented |
OR0405 # 06 Y:2001 | 06 | 2001 | UPGRADE CONTROLS ON COMPRESSORS | $13,877 | $4,000 | Implemented |
OR0405 # 01 Y:2001 | 01 | 2001 | INSTALL EQUIPMENT TO MOVE PRODUCT | $265,366 | $900,000 | Not Implemented |
OR0405 # 07 Y:2001 | 07 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,092 | $13,700 | Not Implemented |
OR0405 # 03 Y:2001 | 03 | 2001 | INSTALL SENSORS TO DETECT AND AVOID JAMS | $116,900 | $20,000 | Not Implemented |
OR0405 # 02 Y:2001 | 02 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $879,623 | $145,450 | Implemented |
MA0500 # 05 Y:2001 | 05 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,562 | $18,000 | Not Implemented |
MA0500 # 03 Y:2001 | 03 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,719 | $20,000 | Not Implemented |
MA0500 # 08 Y:2001 | 08 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,264 | $2,000 | Implemented |
MA0500 # 01 Y:2001 | 01 | 2001 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $47,575 | $350,000 | Not Implemented |
MA0500 # 02 Y:2001 | 02 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $41,719 | $45,000 | Not Implemented |
MA0500 # 04 Y:2001 | 04 | 2001 | OPTIMIZE PLANT POWER FACTOR | $14,725 | $35,000 | Implemented |
MA0500 # 07 Y:2001 | 07 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,051 | $12,900 | Not Implemented |
MA0500 # 06 Y:2001 | 06 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,262 | $10,000 | Not Implemented |
MA0500 # 09 Y:2001 | 09 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,225 | $5,950 | Not Implemented |
OR0401 # 06 Y:2001 | 06 | 2001 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $473,166 | $120,000 | Not Implemented |
OR0401 # 05 Y:2001 | 05 | 2001 | INSTALL SENSORS TO DETECT DEFECTS | $524,500 | $2,000,000 | Not Implemented |
OR0401 # 03 Y:2001 | 03 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $56,333 | $68,000 | Implemented |
OR0401 # 04 Y:2001 | 04 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $560,470 | $690,000 | Not Implemented |
OR0401 # 07 Y:2001 | 07 | 2001 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $270,000 | $50,000 | Not Implemented |
OR0401 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,160 | $6,000 | Implemented |
OR0401 # 01 Y:2001 | 01 | 2001 | OPTIMIZE PLANT POWER FACTOR | $76,739 | $50,000 | Implemented |
OR0400 # 01 Y:2001 | 01 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $210,300 | $750,000 | Not Implemented |
OR0400 # 05 Y:2001 | 05 | 2001 | UPGRADE CONTROLS ON COMPRESSORS | $7,043 | $20,800 | Not Implemented |