Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
23
matching recommendationsSIC | 2435 | Hardwood Veneer And Plywood |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0325 # 01 Y:1998 | 01 | 1998 | ADJUST BURNERS FOR EFFICIENT OPERATION | $5,486 | $500 | Not Implemented |
OR0325 # 02 Y:1998 | 02 | 1998 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $16,215 | $6,816 | Not Implemented |
OR0325 # 03 Y:1998 | 03 | 1998 | ADJUST BURNERS FOR EFFICIENT OPERATION | $4,674 | $0 | Implemented |
OR0325 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,213 | $1,000 | Not Implemented |
OR0325 # 05 Y:1998 | 05 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $970 | $0 | Not Implemented |
UF0205 # 11 Y:1998 | 11 | 1998 | UPGRADE CONVEYORS | $84,000 | $10,500 | Implemented |
UF0205 # 10 Y:1998 | 10 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $17,160 | $10,000 | Implemented |
UF0205 # 09 Y:1998 | 09 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $9,360 | $10,320 | Implemented |
UF0205 # 08 Y:1998 | 08 | 1998 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $21,300 | $45,000 | Not Implemented |
UF0205 # 07 Y:1998 | 07 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,914 | $10,000 | Not Implemented |
UF0205 # 06 Y:1998 | 06 | 1998 | OPTIMIZE PLANT POWER FACTOR | $13,598 | $40,806 | Implemented |
UF0205 # 05 Y:1998 | 05 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,075 | $471 | Implemented |
UF0205 # 04 Y:1998 | 04 | 1998 | OPTIMIZE PLANT POWER FACTOR | $31,516 | $22,000 | Implemented |
UF0205 # 03 Y:1998 | 03 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,422 | $1,215 | Not Implemented |
UF0205 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,997 | $3,200 | Implemented |
UF0205 # 01 Y:1998 | 01 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,940 | $10,390 | Implemented |
NC0131 # 07 Y:1998 | 07 | 1998 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $7,350 | $0 | Not Implemented |
NC0131 # 06 Y:1998 | 06 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $810 | $2,000 | Not Implemented |
NC0131 # 05 Y:1998 | 05 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,092 | $5,200 | Not Implemented |
NC0131 # 04 Y:1998 | 04 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $846 | $0 | Implemented |
NC0131 # 03 Y:1998 | 03 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $7,043 | $0 | Not Implemented |
NC0131 # 02 Y:1998 | 02 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,446 | $9,100 | Not Implemented |
NC0131 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,652 | $0 | Implemented |