Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
171
matching recommendationsSIC | 2436 | Softwood Veneer And Plywood |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0005 # 08 Y:1987 | 08 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,287 | $900 | Implemented |
OR0001 # 01 Y:1987 | 01 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,105 | $0 | Implemented |
OR0001 # 02 Y:1987 | 02 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,491 | $300 | Implemented |
OR0001 # 03 Y:1987 | 03 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $658 | $50 | Implemented |
OR0001 # 05 Y:1987 | 05 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,718 | $2,032 | Implemented |
OR0001 # 06 Y:1987 | 06 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,250 | $1,844 | Implemented |
OR0001 # 07 Y:1987 | 07 | 1987 | OPTIMIZE PLANT POWER FACTOR | $2,856 | $3,960 | Implemented |
LT0071 # 01 Y:1986 | 01 | 1986 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $52,000 | $6,000 | Implemented |
LT0071 # 02 Y:1986 | 02 | 1986 | REDUCE EXCESSIVE BOILER BLOWDOWN | $20,288 | $9,000 | Implemented |
LT0071 # 05 Y:1986 | 05 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $751 | $155 | Implemented |
AT0030 # 02 Y:1985 | 02 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $5,190 | $1,350 | Implemented |
LT0035 # 01 Y:1985 | 01 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $9,541 | $0 | Implemented |
LT0035 # 03 Y:1985 | 03 | 1985 | COVER OPEN TANKS | $1,430 | $720 | Implemented |
LT0035 # 04 Y:1985 | 04 | 1985 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $4,190 | $10,500 | Implemented |
LT0047 # 01 Y:1985 | 01 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,082 | $343 | Implemented |
LT0047 # 02 Y:1985 | 02 | 1985 | REPAIR AND ELIMINATE STEAM LEAKS | $2,990 | $105 | Implemented |
LT0047 # 03 Y:1985 | 03 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $41,000 | $16,000 | Implemented |
LT0034 # 01 Y:1985 | 01 | 1985 | COVER OPEN TANKS | $3,245 | $1,440 | Implemented |
LT0034 # 02 Y:1985 | 02 | 1985 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13,200 | $0 | Implemented |
LT0034 # 03 Y:1985 | 03 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,708 | $0 | Implemented |
LT0034 # 04 Y:1985 | 04 | 1985 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,050 | $417 | Implemented |