Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,712
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0240 # 01 Y:2002 | 01 | 2002 | KEEP BOILER TUBES CLEAN | $12,204 | $10,000 | Implemented |
NC0240 # 02 Y:2002 | 02 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $673 | $1,146 | Implemented |
NC0240 # 03 Y:2002 | 03 | 2002 | USE PHOTOCELL CONTROLS | $118 | $200 | Implemented |
NC0240 # 04 Y:2002 | 04 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $132 | $60 | Implemented |
NC0240 # 05 Y:2002 | 05 | 2002 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $3,000 | $1,000 | Implemented |
NC0240 # 06 Y:2002 | 06 | 2002 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $100,000 | $200,000 | Implemented |
NC0239 # 02 Y:2002 | 02 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $614 | $3,190 | Implemented |
NC0239 # 03 Y:2002 | 03 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $132 | $60 | Implemented |
NC0233 # 02 Y:2002 | 02 | 2002 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $6,359 | $2,000 | Implemented |
NC0233 # 03 Y:2002 | 03 | 2002 | IMPROVE SPACE COMFORT CONDITIONING | $75,150 | $10,000 | Implemented |
NC0233 # 04 Y:2002 | 04 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $293 | $778 | Implemented |
MI0036 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,880 | $52 | Implemented |
MI0036 # 04 Y:2002 | 04 | 2002 | MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE | $8,400 | $995 | Implemented |
MI0036 # 05 Y:2002 | 05 | 2002 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $398 | $250 | Implemented |
MS0205 # 01 Y:2002 | 01 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,065 | $8,070 | Implemented |
MS0205 # 03 Y:2002 | 03 | 2002 | OPTIMIZE PLANT POWER FACTOR | $2,794 | $4,590 | Implemented |
MS0205 # 04 Y:2002 | 04 | 2002 | USE SYNTHETIC LUBRICANT | $1,401 | $396 | Implemented |
MS0205 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $463 | $136 | Implemented |
MS0205 # 06 Y:2002 | 06 | 2002 | DISCONNECT BALLASTS | $438 | $600 | Implemented |
UM0210 # 01 Y:2002 | 01 | 2002 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $43,964 | $148,000 | Implemented |
UM0210 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,037 | $6,600 | Implemented |
UM0210 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,984 | $450 | Implemented |
UM0210 # 05 Y:2002 | 05 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $778 | $900 | Implemented |
IC0030 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,316 | $1,400 | Implemented |
IC0030 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,674 | $27,188 | Implemented |