Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
113
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0463 # 05 Y:2004 | 05 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $11,920 | $12,595 | Not Implemented |
WI0463 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,859 | $29,148 | Not Implemented |
WI0463 # 03 Y:2004 | 03 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,360 | $2,000 | Not Implemented |
WI0463 # 02 Y:2004 | 02 | 2004 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $17,690 | $17,690 | Not Implemented |
WI0463 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,605 | $840 | Not Implemented |
WI0463 # 01 Y:2004 | 01 | 2004 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $75,927 | $18,500 | Not Implemented |
WI0431 # 03 Y:2002 | 03 | 2002 | INSTALL OCCUPANCY SENSORS | $1,532 | $5,000 | Not Implemented |
WI0431 # 04 Y:2002 | 04 | 2002 | INSTALL OCCUPANCY SENSORS | $623 | $300 | Not Implemented |
WI0431 # 06 Y:2002 | 06 | 2002 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $369 | $525 | Not Implemented |
WI0431 # 05 Y:2002 | 05 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $205 | $0 | Implemented |
WI0431 # 08 Y:2002 | 08 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $254 | $90 | Implemented |
WI0431 # 02 Y:2002 | 02 | 2002 | INSTALL TIMERS AND/OR THERMOSTATS | $1,742 | $600 | Implemented |
WI0431 # 01 Y:2002 | 01 | 2002 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $7,907 | $13,000 | Not Implemented |
WI0431 # 07 Y:2002 | 07 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $282 | $640 | Implemented |
WI0410 # 07 Y:2002 | 07 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,255 | $7,140 | Not Implemented |
WI0410 # 01 Y:2002 | 01 | 2002 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $8,178 | $4,800 | Implemented |
WI0410 # 08 Y:2002 | 08 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $942 | $740 | Implemented |
WI0410 # 05 Y:2002 | 05 | 2002 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,885 | $20,800 | Not Implemented |
WI0410 # 02 Y:2002 | 02 | 2002 | INSTALL TIMERS AND/OR THERMOSTATS | $5,395 | $600 | Implemented |
WI0410 # 06 Y:2002 | 06 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,015 | $1,657 | Implemented |
WI0410 # 04 Y:2002 | 04 | 2002 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,636 | $1,050 | Not Implemented |
WI0410 # 03 Y:2002 | 03 | 2002 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,443 | $0 | Not Implemented |
WI0385 # 09 Y:2000 | 09 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,819 | $6,986 | Not Implemented |
WI0385 # 07 Y:2000 | 07 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,895 | $60 | Implemented |
WI0385 # 06 Y:2000 | 06 | 2000 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $3,665 | $1,000 | Not Implemented |