Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
78
matching recommendationsSIC | 251 | Household Furniture |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0123 # 09 Y:1998 | 09 | 1998 | APPLY FOR INVESTMENT INCENTIVES | $110 | $25 | Implemented |
MS0123 # 08 Y:1998 | 08 | 1998 | BURN WOOD BY-PRODUCTS FOR HEAT | $16,438 | $80,000 | Not Implemented |
MS0123 # 07 Y:1998 | 07 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $4,448 | $1,888 | Implemented |
MS0123 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,576 | $389 | Implemented |
MS0123 # 01 Y:1998 | 01 | 1998 | DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING | $1,920 | $1,520 | Implemented |
MS0123 # 06 Y:1998 | 06 | 1998 | OPTIMIZE PLANT POWER FACTOR | $11,310 | $10,800 | Implemented |
MS0123 # 03 Y:1998 | 03 | 1998 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $3,682 | $13,606 | Not Implemented |
MS0123 # 04 Y:1998 | 04 | 1998 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,528 | $1,892 | Not Implemented |
MS0123 # 02 Y:1998 | 02 | 1998 | USE RADIANT HEATER FOR SPOT HEATING | $7,783 | $9,763 | Implemented |
SF0150 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $75 | $147 | Implemented |
SF0150 # 01 Y:1998 | 01 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $300 | $260 | Not Implemented |
SF0150 # 04 Y:1998 | 04 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $5,375 | $0 | Implemented |
SF0150 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,331 | $22,713 | Not Implemented |
MS0118 # 02 Y:1998 | 02 | 1998 | OPTIMIZE PLANT POWER FACTOR | $818 | $390 | Implemented |
MS0118 # 01 Y:1998 | 01 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,152 | $925 | Implemented |
MS0118 # 03 Y:1998 | 03 | 1998 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $777 | $20 | Implemented |
MS0118 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $698 | $469 | Implemented |
MS0118 # 05 Y:1998 | 05 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $10,474 | $1,968 | Implemented |
UD0551 # 01 Y:1998 | 01 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $42,000 | $2,400 | Not Implemented |
UD0551 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,897 | $10,073 | Implemented |
UD0551 # 03 Y:1998 | 03 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $2,400 | $7,000 | Not Implemented |
UD0551 # 04 Y:1998 | 04 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $1,083 | $225 | Implemented |
MO0230 # 01 Y:1998 | 01 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $86,930 | $91,375 | Implemented |
MO0230 # 09 Y:1998 | 09 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $93,928 | $39,600 | Not Implemented |
MO0230 # 10 Y:1998 | 10 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $63,165 | $15,100 | Implemented |