Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,948
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0371 # 03 Y:1996 | 03 | 1996 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $22,269 | $15,000 | Implemented |
MA0371 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $39,790 | $174,574 | Implemented |
MA0371 # 05 Y:1996 | 05 | 1996 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,688 | $2,508 | Not Implemented |
WI0278 # 01 Y:1996 | 01 | 1996 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $141,768 | $412,500 | Not Implemented |
WI0278 # 02 Y:1996 | 02 | 1996 | INSTALL SET-BACK TIMERS | $15,919 | $2,400 | Implemented |
WI0278 # 03 Y:1996 | 03 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $11,230 | $500 | Implemented |
WI0278 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,105 | $11,072 | Not Implemented |
WI0278 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,241 | $1,786 | Not Implemented |
WI0278 # 06 Y:1996 | 06 | 1996 | MINIMIZE WATER USAGE | $5,933 | $1,000 | Implemented |
WI0278 # 07 Y:1996 | 07 | 1996 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,818 | $0 | Implemented |
WI0278 # 08 Y:1996 | 08 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $976 | $505 | Not Implemented |
WI0278 # 09 Y:1996 | 09 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $546 | $0 | Implemented |
WI0278 # 10 Y:1996 | 10 | 1996 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,441 | $8,360 | Not Implemented |
WI0278 # 11 Y:1996 | 11 | 1996 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,999 | $10,000 | Implemented |
WI0278 # 12 Y:1996 | 12 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,899 | $740 | Implemented |
WI0278 # 13 Y:1996 | 13 | 1996 | MINIMIZE WATER USAGE | $1,424 | $0 | Implemented |
BD0068 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,122 | $12,270 | Implemented |
BD0068 # 02 Y:1996 | 02 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,590 | $800 | Implemented |
BD0068 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,611 | $2,563 | Implemented |
BD0068 # 04 Y:1996 | 04 | 1996 | INSTALL OCCUPANCY SENSORS | $1,441 | $1,500 | Not Implemented |
BD0068 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,531 | $2,590 | Implemented |
BD0068 # 06 Y:1996 | 06 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,111 | $1,020 | Implemented |
BD0068 # 07 Y:1996 | 07 | 1996 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $562 | $660 | Not Implemented |
BD0068 # 08 Y:1996 | 08 | 1996 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $11,996 | $9,045 | Not Implemented |
UL0168 # 01 Y:1996 | 01 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,936 | $1,400 | Implemented |