Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
348
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0787 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,714 | $2,828 | Not Implemented |
UD0787 # 08 Y:2008 | 08 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,656 | $0 | Not Implemented |
UD0787 # 09 Y:2008 | 09 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,351 | $1,000 | Implemented |
UD0787 # 10 Y:2008 | 10 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $388 | $1,000 | Implemented |
WV0314 # 13 Y:2005 | 13 | 2005 | CONDENSE OPERATION INTO ONE BUILDING | $44,003 | $60,000 | Not Implemented |
WV0314 # 12 Y:2005 | 12 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $217 | $215 | Not Implemented |
WV0314 # 11 Y:2005 | 11 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $406 | $96 | Implemented |
WV0314 # 10 Y:2005 | 10 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $426 | $358 | Not Implemented |
WV0314 # 09 Y:2005 | 09 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $461 | $138 | Not Implemented |
WV0314 # 08 Y:2005 | 08 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $534 | $105 | Implemented |
WV0314 # 07 Y:2005 | 07 | 2005 | INSULATE BARE EQUIPMENT | $1,552 | $404 | Implemented |
WV0314 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,829 | $605 | Implemented |
WV0314 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,404 | $5,877 | Not Implemented |
WV0314 # 04 Y:2005 | 04 | 2005 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $4,156 | $9,591 | Not Implemented |
WV0314 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,828 | $0 | Implemented |
WV0314 # 02 Y:2005 | 02 | 2005 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $14,277 | $70 | Implemented |
WV0314 # 01 Y:2005 | 01 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $14,732 | $3,713 | Implemented |
WV0294 # 04 Y:2004 | 04 | 2004 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $4,247 | $2,660 | Implemented |
WV0294 # 05 Y:2004 | 05 | 2004 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $509,116 | $20,000 | Not Implemented |
WV0294 # 10 Y:2004 | 10 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $232 | $129 | Not Implemented |
WV0294 # 06 Y:2004 | 06 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,472 | $920 | Implemented |
WV0294 # 07 Y:2004 | 07 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,431 | $784 | Implemented |
WV0294 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,317 | $215 | Implemented |
WV0294 # 09 Y:2004 | 09 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $609 | $46 | Implemented |
WV0294 # 03 Y:2004 | 03 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $5,704 | $230 | Implemented |