Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
193
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0284 # 01 Y:2020 | 01 | 2020 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,928 | $750 | Implemented |
MZ0284 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $14,842 | $19,695 | Implemented |
MZ0284 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,835 | $640 | Implemented |
MZ0284 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,092 | $320 | Implemented |
MZ0181 # 04 Y:2015 | 04 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,719 | $0 | Implemented |
MZ0147 # 10 Y:2014 | 10 | 2014 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $3,158 | $250 | Implemented |
MZ0147 # 03 Y:2014 | 03 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $63 | $235 | Implemented |
MZ0147 # 06 Y:2014 | 06 | 2014 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,184 | $600 | Implemented |
MZ0147 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,562 | $42,645 | Implemented |
MZ0147 # 09 Y:2014 | 09 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,212 | $420 | Implemented |
MZ0147 # 01 Y:2014 | 01 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $871 | $360 | Implemented |
MZ0147 # 02 Y:2014 | 02 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $63 | $235 | Implemented |
MZ0147 # 04 Y:2014 | 04 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $423 | $470 | Implemented |
MZ0122 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $1,742 | $1,240 | Implemented |
MZ0122 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,872 | $1,308 | Implemented |
MZ0122 # 07 Y:2013 | 07 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,732 | $281 | Implemented |
MZ0122 # 09 Y:2013 | 09 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $576 | $500 | Implemented |
MZ0122 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,176 | $4,981 | Implemented |
MZ0122 # 03 Y:2013 | 03 | 2013 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,627 | $1,000 | Implemented |
MZ0122 # 01 Y:2013 | 01 | 2013 | INSULATE BARE EQUIPMENT | $21,142 | $3,276 | Implemented |
MZ0098 # 07 Y:2012 | 07 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,271 | $1,283 | Implemented |
MZ0098 # 04 Y:2012 | 04 | 2012 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $9,018 | $250 | Implemented |
MZ0098 # 02 Y:2012 | 02 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $42,267 | $26,000 | Implemented |
MZ0098 # 01 Y:2012 | 01 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $57,632 | $23,700 | Implemented |
MZ0098 # 05 Y:2012 | 05 | 2012 | INSTALL OCCUPANCY SENSORS | $5,896 | $3,000 | Implemented |