Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
303
matching recommendationsSIC | 265 | Paperboard Containers And Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0096 # 01 Y:2005 | 01 | 2005 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $13,200 | $25,840 | Not Implemented |
AM0487 # 01 Y:2005 | 01 | 2005 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $108,000 | $24,500 | Not Implemented |
AM0487 # 02 Y:2005 | 02 | 2005 | OPTIMIZE PLANT POWER FACTOR | $27,000 | $61,600 | Not Implemented |
AM0487 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,460 | $500 | Not Implemented |
AM0487 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $10,400 | $1,200 | Not Implemented |
AM0487 # 05 Y:2005 | 05 | 2005 | USE PHOTOCELL CONTROLS | $2,600 | $100 | Not Implemented |
AM0487 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,700 | $2,100 | Not Implemented |
AM0487 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $920 | $500 | Not Implemented |
AM0487 # 08 Y:2005 | 08 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,940 | $4,200 | Not Implemented |
TA0071 # 11 Y:2004 | 11 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $307 | $0 | Not Implemented |
TA0071 # 10 Y:2004 | 10 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,150 | $340 | Implemented |
TA0071 # 09 Y:2004 | 09 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,330 | $300 | Not Implemented |
TA0071 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,930 | $400 | Implemented |
TA0071 # 07 Y:2004 | 07 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,940 | $600 | Not Implemented |
TA0071 # 06 Y:2004 | 06 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,525 | $175 | Not Implemented |
TA0071 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $6,180 | $930 | Not Implemented |
TA0071 # 04 Y:2004 | 04 | 2004 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $8,400 | $0 | Not Implemented |
TA0071 # 03 Y:2004 | 03 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $14,500 | $550 | Implemented |
TA0071 # 02 Y:2004 | 02 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $15,600 | $12,000 | Not Implemented |
TA0071 # 01 Y:2004 | 01 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $18,700 | $0 | Implemented |
TA0064 # 07 Y:2003 | 07 | 2003 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $101 | $211 | Implemented |
TA0064 # 01 Y:2003 | 01 | 2003 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $9,350 | $1,800 | Implemented |
TA0064 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,035 | $0 | Not Implemented |
TA0064 # 05 Y:2003 | 05 | 2003 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $1,740 | $520 | Implemented |
TA0064 # 04 Y:2003 | 04 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,770 | $0 | Implemented |