Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
53
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0286 # 11 Y:2002 | 11 | 2002 | INSTALL EQUIPMENT TO MOVE PRODUCT | $-1,412 | $80,000 | Not Implemented |
IA0286 # 10 Y:2002 | 10 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,028 | $2,680 | Not Implemented |
IA0286 # 09 Y:2002 | 09 | 2002 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $2,570 | $3,500 | Not Implemented |
IA0286 # 08 Y:2002 | 08 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $2,691 | $1,000 | Implemented |
IA0286 # 07 Y:2002 | 07 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,270 | $1,500 | Implemented |
IA0286 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,320 | $0 | Implemented |
IA0286 # 05 Y:2002 | 05 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,465 | $16,361 | Implemented |
IA0286 # 04 Y:2002 | 04 | 2002 | INSTALL OCCUPANCY SENSORS | $1,353 | $3,186 | Not Implemented |
IA0286 # 03 Y:2002 | 03 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,022 | $25 | Not Implemented |
IA0286 # 02 Y:2002 | 02 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,616 | $250 | Implemented |
IA0286 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,555 | $434 | Implemented |
DS0134 # 06 Y:1999 | 06 | 1999 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $8,437 | $1,350 | Not Implemented |
DS0134 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,978 | $161 | Implemented |
DS0134 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $885 | $625 | Implemented |
DS0134 # 04 Y:1999 | 04 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $787 | $1,551 | Not Implemented |
DS0134 # 05 Y:1999 | 05 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $455 | $240 | Implemented |
DS0134 # 02 Y:1999 | 02 | 1999 | OPTIMIZE PLANT POWER FACTOR | $1,209 | $1,750 | Not Implemented |
DS0132 # 03 Y:1999 | 03 | 1999 | OPTIMIZE PLANT POWER FACTOR | $869 | $1,750 | Not Implemented |
DS0132 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $947 | $113 | Not Implemented |
DS0132 # 01 Y:1999 | 01 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $1,316 | $1,705 | Not Implemented |
DS0132 # 09 Y:1999 | 09 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $795 | $90 | Not Implemented |
DS0132 # 08 Y:1999 | 08 | 1999 | INSTALL SYSTEM TO COLLECT SCRAP | $13,520 | $6,260 | Not Implemented |
DS0132 # 06 Y:1999 | 06 | 1999 | MAINTAIN MACHINES TO REDUCE LEAKS | $2,049 | $52 | Not Implemented |
DS0132 # 07 Y:1999 | 07 | 1999 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $5,579 | $2,750 | Not Implemented |
DS0132 # 04 Y:1999 | 04 | 1999 | INSTALL OCCUPANCY SENSORS | $232 | $108 | Not Implemented |