Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsSIC | 2679 | Converted Paper Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0161 # 06 Y:2000 | 06 | 2000 | PAY UTILITY BILLS ON TIME | $204 | $0 | Not Implemented |
OD0161 # 05 Y:2000 | 05 | 2000 | REPAIR OR REPLACE STEAM TRAPS | $2,084 | $700 | Not Implemented |
OD0161 # 04 Y:2000 | 04 | 2000 | REPAIR AND ELIMINATE STEAM LEAKS | $1,013 | $1,360 | Not Implemented |
OD0161 # 03 Y:2000 | 03 | 2000 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,027 | $1,500 | Not Implemented |
OD0161 # 02 Y:2000 | 02 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $3,900 | $3,000 | Not Implemented |
OD0161 # 01 Y:2000 | 01 | 2000 | INSULATE BARE EQUIPMENT | $2,365 | $5,892 | Not Implemented |
OD0037 # 05 Y:1995 | 05 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,883 | $480 | Implemented |
OD0037 # 09 Y:1995 | 09 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,437 | $910 | Implemented |
OD0037 # 08 Y:1995 | 08 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $994 | $0 | Not Implemented |
OD0037 # 07 Y:1995 | 07 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $477 | $0 | Implemented |
OD0037 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $545 | $433 | Not Implemented |
OD0037 # 04 Y:1995 | 04 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $720 | $1,035 | Not Implemented |
OD0037 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $612 | $748 | Implemented |
OD0037 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,607 | $635 | Not Implemented |
OD0037 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,053 | $726 | Implemented |
OD0001 # 01 Y:1994 | 01 | 1994 | INSULATE BARE EQUIPMENT | $1,054 | $633 | Implemented |
OD0001 # 07 Y:1994 | 07 | 1994 | REPAIR OR REPLACE STEAM TRAPS | $669 | $400 | Not Implemented |
OD0001 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,686 | $2,315 | Implemented |
OD0001 # 05 Y:1994 | 05 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,155 | $800 | Implemented |
OD0001 # 04 Y:1994 | 04 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $426 | $600 | Implemented |
OD0001 # 03 Y:1994 | 03 | 1994 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $2,303 | $0 | Not Implemented |
OD0001 # 02 Y:1994 | 02 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $345 | $200 | Implemented |