Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,540
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0807 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $719 | $663 | Implemented |
GT0807 # 03 Y:2005 | 03 | 2005 | INSTALL OCCUPANCY SENSORS | $1,135 | $543 | Implemented |
GT0807 # 04 Y:2005 | 04 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $427 | $120 | Implemented |
GT0807 # 08 Y:2005 | 08 | 2005 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $497 | $1,300 | Implemented |
UD0717 # 01 Y:2005 | 01 | 2005 | INCREASE USE OF AUTOMATION | $68,000 | $145,000 | Implemented |
UD0717 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,783 | $39,200 | Implemented |
UD0717 # 04 Y:2005 | 04 | 2005 | REPAIR OR REPLACE STEAM TRAPS | $12,702 | $5,400 | Implemented |
UD0717 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,225 | $0 | Implemented |
UD0717 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,553 | $11,448 | Implemented |
UD0717 # 09 Y:2005 | 09 | 2005 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $3,658 | $2,526 | Implemented |
WI0491 # 03 Y:2005 | 03 | 2005 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,911 | $5,000 | Implemented |
WI0491 # 05 Y:2005 | 05 | 2005 | INSTALL OCCUPANCY SENSORS | $1,112 | $1,680 | Implemented |
WI0491 # 06 Y:2005 | 06 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $706 | $1,244 | Implemented |
IC0097 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,330 | $700 | Implemented |
IC0097 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,092 | $41,838 | Implemented |
SF0294 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,133 | $0 | Implemented |
SF0294 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,414 | $22,970 | Implemented |
UD0705 # 01 Y:2004 | 01 | 2004 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $50,000 | $50,000 | Implemented |
UD0705 # 03 Y:2004 | 03 | 2004 | REDUCE SCRAP PRODUCTION | $12,990 | $0 | Implemented |
UD0705 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,683 | $0 | Implemented |
UD0705 # 09 Y:2004 | 09 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $1,214 | $0 | Implemented |
UD0705 # 10 Y:2004 | 10 | 2004 | COVER OPEN TANKS | $710 | $0 | Implemented |
UD0705 # 11 Y:2004 | 11 | 2004 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $83 | $0 | Implemented |
UD0703 # 01 Y:2004 | 01 | 2004 | REDUCE SCRAP PRODUCTION | $45,630 | $650 | Implemented |
UD0703 # 02 Y:2004 | 02 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $5,110 | $0 | Implemented |