Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
174
matching recommendationsSIC | 275 | Commercial Printing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1075 # 05 Y:2024 | 05 | 2024 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $712 | $0 | Implemented |
UD1075 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $829 | $0 | Implemented |
UD1075 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,737 | $952 | Implemented |
UD1075 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,565 | $2,238 | Implemented |
UD1075 # 06 Y:2024 | 06 | 2024 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $5,142 | $25,000 | Not Implemented |
UD1075 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,038 | $7,596 | Implemented |
UD1075 # 07 Y:2024 | 07 | 2024 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $712,662 | $195,000 | Implemented |
WV0453 # 08 Y:2012 | 08 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $981 | $1,400 | Not Implemented |
WV0453 # 06 Y:2012 | 06 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $1,960 | $2,450 | Not Implemented |
WV0453 # 05 Y:2012 | 05 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $2,222 | $938 | Not Implemented |
WV0453 # 04 Y:2012 | 04 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,045 | $0 | Not Implemented |
WV0453 # 03 Y:2012 | 03 | 2012 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $4,494 | $12,500 | Not Implemented |
WV0453 # 01 Y:2012 | 01 | 2012 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,920 | $0 | Implemented |
WV0453 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $9,963 | $2,600 | Not Implemented |
WV0453 # 07 Y:2012 | 07 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,239 | $1,000 | Implemented |
WV0453 # 11 Y:2012 | 11 | 2012 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $251 | $800 | Not Implemented |
WV0453 # 10 Y:2012 | 10 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $753 | $25 | Not Implemented |
WV0453 # 12 Y:2012 | 12 | 2012 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $115 | $100 | Implemented |
WV0453 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $834 | $375 | Implemented |
WV0335 # 04 Y:2006 | 04 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $6,057 | $240 | Implemented |
WV0335 # 08 Y:2006 | 08 | 2006 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $985 | $1,680 | Implemented |
WV0335 # 03 Y:2006 | 03 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,924 | $250 | Not Implemented |
WV0335 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,865 | $1,420 | Implemented |
WV0335 # 01 Y:2006 | 01 | 2006 | USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION | $151,578 | $97,142 | Not Implemented |
WV0335 # 07 Y:2006 | 07 | 2006 | BURN WASTE OIL FOR HEAT | $1,494 | $1,300 | Not Implemented |