Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,216
matching recommendationsSIC | 2759 | Commercial Printing, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0211 # 13 Y:1998 | 13 | 1998 | MODIFY STORAGE SPACE TO AVOID RENTAL OF A WAREHOUSE | $172,000 | $150,000 | Implemented |
DS0117 # 01 Y:1998 | 01 | 1998 | OPTIMIZE PLANT POWER FACTOR | $3,377 | $2,787 | Not Implemented |
DS0117 # 02 Y:1998 | 02 | 1998 | USE POWER DURING OFF-PEAK PERIODS | $667 | $556 | Not Implemented |
DS0117 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $752 | $750 | Not Implemented |
DS0117 # 04 Y:1998 | 04 | 1998 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,856 | $2,650 | Not Implemented |
DS0117 # 05 Y:1998 | 05 | 1998 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $10,453 | $6,000 | Not Implemented |
DS0117 # 06 Y:1998 | 06 | 1998 | INCREASE USE OF AUTOMATION | $27,300 | $4,900 | Not Implemented |
SF0140 # 01 Y:1998 | 01 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $10,516 | $240 | Not Implemented |
SF0140 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,893 | $2,924 | Not Implemented |
SF0140 # 03 Y:1998 | 03 | 1998 | INSTALL OCCUPANCY SENSORS | $2,197 | $1,728 | Not Implemented |
SF0140 # 04 Y:1998 | 04 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,117 | $858 | Not Implemented |
SF0140 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,307 | $36,660 | Not Implemented |
SF0140 # 06 Y:1998 | 06 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,230 | $13,240 | Not Implemented |
SF0140 # 07 Y:1998 | 07 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $259 | $702 | Not Implemented |
SF0140 # 08 Y:1998 | 08 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $5,866 | $0 | Not Implemented |
SF0140 # 09 Y:1998 | 09 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $3,642 | $200 | Not Implemented |
SF0140 # 10 Y:1998 | 10 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $7,861 | $8,700 | Not Implemented |
SF0140 # 11 Y:1998 | 11 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $12,856 | $10,280 | Not Implemented |
SF0140 # 12 Y:1998 | 12 | 1998 | RECYCLE CLEANING SOLVENT AND REUSE | $13,860 | $40,000 | Not Implemented |
IA0189 # 01 Y:1998 | 01 | 1998 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $4,134 | $4,000 | Not Implemented |
IA0189 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,819 | $16,391 | Implemented |
IA0189 # 03 Y:1998 | 03 | 1998 | RECOVER AND REUSE WASTE MATERIAL | $2,357 | $500 | Implemented |
IA0189 # 04 Y:1998 | 04 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $423 | $200 | Not Implemented |
IA0189 # 05 Y:1998 | 05 | 1998 | USE SYNTHETIC LUBRICANT | $349 | $173 | Implemented |
WI0313 # 01 Y:1998 | 01 | 1998 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $4,445 | $7,155 | Implemented |