Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
81
matching recommendationsSIC | 28 | Chemicals And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0370 # 07 Y:2005 | 07 | 2005 | INSULATE BARE EQUIPMENT | $4,053 | $1,317 | Implemented |
UF0370 # 03 Y:2005 | 03 | 2005 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $20,435 | $56,000 | Implemented |
UF0370 # 01 Y:2005 | 01 | 2005 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,736 | $1,212 | Implemented |
UF0370 # 11 Y:2005 | 11 | 2005 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,313 | $0 | Implemented |
UF0370 # 09 Y:2005 | 09 | 2005 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $47,299 | $130,000 | Implemented |
AS0411 # 06 Y:2005 | 06 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $4,077 | $8,000 | Implemented |
AS0411 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,306 | $1,000 | Implemented |
WV0327 # 06 Y:2005 | 06 | 2005 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,057 | $696 | Implemented |
WV0327 # 04 Y:2005 | 04 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,759 | $1,000 | Implemented |
WV0327 # 03 Y:2005 | 03 | 2005 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,323 | $3,960 | Implemented |
WV0327 # 08 Y:2005 | 08 | 2005 | USE SYNTHETIC LUBRICANT | $415 | $24 | Implemented |
WV0327 # 14 Y:2005 | 14 | 2005 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,365 | $96 | Implemented |
WV0327 # 12 Y:2005 | 12 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $246 | $0 | Implemented |
WV0327 # 09 Y:2005 | 09 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $388 | $176 | Implemented |
WV0327 # 13 Y:2005 | 13 | 2005 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $224 | $120 | Implemented |
WV0327 # 10 Y:2005 | 10 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $342 | $60 | Implemented |
WV0327 # 01 Y:2005 | 01 | 2005 | INSULATE BARE EQUIPMENT | $11,686 | $2,140 | Implemented |
OK0718 # 06 Y:2005 | 06 | 2005 | INSULATE BARE EQUIPMENT | $1,343 | $1,693 | Implemented |
OK0718 # 07 Y:2005 | 07 | 2005 | USE OPTIMUM THICKNESS INSULATION | $2,162 | $1,710 | Implemented |
OK0718 # 08 Y:2005 | 08 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,226 | $66,500 | Implemented |
OK0718 # 01 Y:2005 | 01 | 2005 | DEVELOP A REPAIR/REPLACE POLICY | $12,970 | $500 | Implemented |
AM0496 # 02 Y:2005 | 02 | 2005 | OPTIMIZE PLANT POWER FACTOR | $6,400 | $8,050 | Implemented |
AM0496 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,400 | $5 | Implemented |
AM0496 # 03 Y:2005 | 03 | 2005 | PAY UTILITY BILLS ON TIME | $1,448 | $0 | Implemented |
AM0496 # 06 Y:2005 | 06 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $110 | $0 | Implemented |