Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
514
matching recommendationsSIC | 2821 | Plastics Materials And Resins |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0160 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,924 | $17,420 | Implemented |
IC0160 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $292 | $653 | Implemented |
IC0160 # 05 Y:2009 | 05 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $42,819 | $131,206 | Implemented |
IC0160 # 06 Y:2009 | 06 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $17,221 | $42,838 | Implemented |
IC0160 # 07 Y:2009 | 07 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,043 | $345 | Implemented |
IC0160 # 08 Y:2009 | 08 | 2009 | REPAIR AND ELIMINATE STEAM LEAKS | $746 | $58 | Implemented |
IC0160 # 10 Y:2009 | 10 | 2009 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $179 | $0 | Implemented |
UW0026 # 03 Y:2009 | 03 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,086 | $19,000 | Implemented |
UW0026 # 04 Y:2009 | 04 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,037 | $0 | Implemented |
UW0026 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,715 | $200 | Implemented |
UW0026 # 06 Y:2009 | 06 | 2009 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $11,522 | $19,854 | Implemented |
DL0025 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,976 | $0 | Implemented |
DL0025 # 03 Y:2008 | 03 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $36,900 | $0 | Implemented |
DL0025 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,919 | $30,000 | Implemented |
OR0534 # 03 Y:2008 | 03 | 2008 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,794 | $0 | Implemented |
OR0534 # 04 Y:2008 | 04 | 2008 | OPTIMIZE PLANT POWER FACTOR | $6,768 | $6,825 | Implemented |
OR0534 # 05 Y:2008 | 05 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $271 | $0 | Implemented |
OR0534 # 08 Y:2008 | 08 | 2008 | INSTALL OCCUPANCY SENSORS | $1,219 | $2,510 | Implemented |
OR0534 # 10 Y:2008 | 10 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $447 | $808 | Implemented |
DL0017 # 03 Y:2008 | 03 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,007 | $800 | Implemented |
DL0017 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,006 | $26,496 | Implemented |
DL0013 # 01 Y:2008 | 01 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $18,300 | $0 | Implemented |
DL0013 # 02 Y:2008 | 02 | 2008 | INSTALL OCCUPANCY SENSORS | $2,396 | $285 | Implemented |
DL0013 # 03 Y:2008 | 03 | 2008 | INSULATE BARE EQUIPMENT | $108,300 | $104,800 | Implemented |
DL0013 # 04 Y:2008 | 04 | 2008 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $24,218 | $25,000 | Implemented |