Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

59

matching recommendations
Reset
SIC 2834 Pharmaceutical Preparations
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0479 # 09 Y:2013 09 2013 INSULATE BARE EQUIPMENT $533 $350 Implemented
NC0479 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $99 $351 Implemented
NC0479 # 04 Y:2013 04 2013 RECOVER WASTE HEAT FROM EQUIPMENT $1,378 $3,750 Not Implemented
NC0479 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,261 $100 Implemented
NC0479 # 07 Y:2013 07 2013 USE PHOTOCELL CONTROLS $106 $250 Implemented
NC0479 # 01 Y:2013 01 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $9,663 $40,000 Not Implemented
NC0479 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $238 $1,102 Implemented
NC0479 # 08 Y:2013 08 2013 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,059 $2,867 Not Implemented
NC0479 # 02 Y:2013 02 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $6,601 $10,000 Implemented
NC0443 # 06 Y:2012 06 2012 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $28,327 $96,000 Not Implemented
NC0443 # 05 Y:2012 05 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $633 $2,440 Not Implemented
NC0443 # 04 Y:2012 04 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $3,960 $10,175 Not Implemented
NC0443 # 03 Y:2012 03 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,514 $500 Not Implemented
NC0443 # 02 Y:2012 02 2012 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $9,610 $27,000 Not Implemented
NC0443 # 01 Y:2012 01 2012 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM $24,834 $105,200 Not Implemented
NC0370 # 06 Y:2007 06 2007 MINIMIZE WATER USAGE $74,891 $121,780 Not Implemented
NC0370 # 07 Y:2007 07 2007 RECOVER WASTE HEAT FROM EQUIPMENT $87,257 $136,000 Not Implemented
NC0370 # 08 Y:2007 08 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $48,768 $120,500 Not Implemented
NC0370 # 10 Y:2007 10 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,644 $7,240 Not Implemented
NC0370 # 09 Y:2007 09 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,690 $50 Not Implemented
NC0370 # 05 Y:2007 05 2007 RECOVER WASTE HEAT FROM EQUIPMENT $45,052 $88,200 Not Implemented
NC0370 # 04 Y:2007 04 2007 RECOVER WASTE HEAT FROM EQUIPMENT $27,567 $74,816 Not Implemented
NC0370 # 03 Y:2007 03 2007 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $48,420 $25,000 Not Implemented
NC0370 # 02 Y:2007 02 2007 REPAIR OR REPLACE STEAM TRAPS $43,809 $17,100 Not Implemented
NC0370 # 01 Y:2007 01 2007 ADJUST BURNERS FOR EFFICIENT OPERATION $30,975 $65,000 Not Implemented