Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
33
matching recommendationsSIC | 2835 | Diagnostic Substances |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0572 # 05 Y:2018 | 05 | 2018 | INSTALL OCCUPANCY SENSORS | $349 | $378 | Implemented |
SD0572 # 04 Y:2018 | 04 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $970 | $1,350 | Implemented |
SD0572 # 03 Y:2018 | 03 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,372 | $0 | Implemented |
SD0572 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,304 | $22,430 | Implemented |
SD0572 # 01 Y:2018 | 01 | 2018 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $75,389 | $234,915 | Implemented |
SF0337 # 01 Y:2007 | 01 | 2007 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $9,667 | $0 | Implemented |
SF0337 # 03 Y:2007 | 03 | 2007 | INSULATE BARE EQUIPMENT | $1,729 | $937 | Implemented |
SF0337 # 04 Y:2007 | 04 | 2007 | INSTALL OCCUPANCY SENSORS | $3,650 | $3,344 | Implemented |
SF0337 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,534 | $3,510 | Implemented |
SF0337 # 06 Y:2007 | 06 | 2007 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,179 | $3,376 | Implemented |
SF0336 # 11 Y:2006 | 11 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $955 | $2,480 | Implemented |
SF0336 # 13 Y:2006 | 13 | 2006 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $327 | $6,381 | Implemented |
SF0336 # 10 Y:2006 | 10 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $234 | $557 | Implemented |
SF0336 # 09 Y:2006 | 09 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2 | $7,040 | Implemented |
SF0336 # 02 Y:2006 | 02 | 2006 | REDUCE VENTILATION AIR | $202 | $0 | Implemented |
SF0336 # 01 Y:2006 | 01 | 2006 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $16 | $0 | Implemented |
SF0336 # 12 Y:2006 | 12 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,076 | $16,625 | Implemented |
SD0231 # 03 Y:1999 | 03 | 1999 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $7,020 | $0 | Implemented |
SD0231 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,674 | $10,286 | Implemented |
SD0076 # 11 Y:1994 | 11 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,149 | $630 | Implemented |
SD0076 # 10 Y:1994 | 10 | 1994 | INSTALL OCCUPANCY SENSORS | $1,267 | $3,760 | Implemented |
SD0076 # 09 Y:1994 | 09 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $457 | $552 | Implemented |
SD0076 # 07 Y:1994 | 07 | 1994 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,072 | $2,416 | Implemented |
SD0076 # 03 Y:1994 | 03 | 1994 | INSULATE BARE EQUIPMENT | $263 | $512 | Implemented |
SD0076 # 02 Y:1994 | 02 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,732 | $20 | Implemented |