Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
349
matching recommendationsSIC | 2851 | Paints And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0596 # 03 Y:2006 | 03 | 2006 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $10,740 | $5,440 | Implemented |
MA0596 # 04 Y:2006 | 04 | 2006 | USE UTILITY CONTROLLED POWER MANAGEMENT | $9,148 | $4,500 | Implemented |
MA0596 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,400 | $37,895 | Implemented |
MA0596 # 06 Y:2006 | 06 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,195 | $13,000 | Implemented |
MA0596 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $4,855 | $8,000 | Implemented |
MA0596 # 09 Y:2006 | 09 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,026 | $5,350 | Implemented |
MA0596 # 10 Y:2006 | 10 | 2006 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $2,415 | $9,840 | Implemented |
AM0496 # 02 Y:2005 | 02 | 2005 | OPTIMIZE PLANT POWER FACTOR | $6,400 | $8,050 | Implemented |
AM0496 # 03 Y:2005 | 03 | 2005 | PAY UTILITY BILLS ON TIME | $1,448 | $0 | Implemented |
AM0496 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,400 | $5 | Implemented |
AM0496 # 06 Y:2005 | 06 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $110 | $0 | Implemented |
OK0709 # 02 Y:2005 | 02 | 2005 | INSULATE BARE EQUIPMENT | $3,684 | $1,030 | Implemented |
MA0573 # 01 Y:2005 | 01 | 2005 | INSTALL TIMERS AND/OR THERMOSTATS | $15,507 | $6,435 | Implemented |
MA0573 # 04 Y:2005 | 04 | 2005 | INSULATE BARE EQUIPMENT | $2,868 | $3,920 | Implemented |
IC0091 # 01 Y:2004 | 01 | 2004 | REPAIR OR REPLACE STEAM TRAPS | $1,701 | $638 | Implemented |
IC0091 # 02 Y:2004 | 02 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,038 | $1,315 | Implemented |
IC0091 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,889 | $1,265 | Implemented |
WV0304 # 11 Y:2004 | 11 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $418 | $154 | Implemented |
WV0304 # 10 Y:2004 | 10 | 2004 | INSULATE BARE EQUIPMENT | $509 | $44 | Implemented |
WV0304 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,376 | $0 | Implemented |
WV0304 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,679 | $22 | Implemented |
WV0304 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,051 | $210 | Implemented |
WV0304 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $5,483 | $4,491 | Implemented |
WV0304 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,964 | $2,752 | Implemented |
IC0075 # 07 Y:2004 | 07 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,105 | $2,900 | Implemented |